Activate Procurement Clause Phrase Revision
Explanation
This activity is used to activate the procurement clause phrase revision. Only active procurement clause phrase
revisions will be available for source line connections.
This is an irreversible activity, hence should be done only after reviewing and finalization of phrase text.
Prerequisites
- Phrase revision status should be Inactive or Approved.
- Phrase text should be defined in at least one language.
- Valid time period of this revision should not overlap with the valid time period of another active
revision.
System Effects
As a result of this activity,
- Phrase revision status is set to Active.
- Procurement clause phrase generation logic will consider this revision as a valid candidate for connection
with source lines.
- Phrase revision will be available for users to manually connect to a source line.