Connect to Project Activity
Explanation
This activity is used to manually connect a purchase requisition line(s) to a project activity from the create
purchase requisition assistant. This activity is performed to obtain the cost of the project activity of goods
being requested for the project through the purchase requisition. This is an optional step in the assistant.
Note: All lines included in the purchase requisition will be connected to the same project.
Prerequisites
- The project to be connected must be in the Approved or Started status.
- The project activity must be in the Planned or Released status to be available.
- The purchase requisition line should not have any exchange components.
- The site of the purchase requisition line must have been defined as an allowed site for the connected
project.
- The relevant posting type must have been specified for the project code part.
- The project code part must not have been pre-posted with a financial project.
- Project manual connections to the purchase requisition lines must have been made available on the Project
Details/Project Manual Connections tab.
System Effects
- All lines included in the purchase requisition will be connected to the specified project.