Enter Performed Interval Based Maintenance

Explanation

This activity is used to enter interval based maintenance activities that have been previously performed on the serial structure, but not yet been logged in the system. You can enter this information for both components that have not been logged in the system before, and components that have existing, but not complete, historical data in the system. It is possible to adjust the values that were recently entered so that several records do not appear in the log by mistake. The Serial Initialization/Interval Maintenance tab displays all possible maintenance activities, not only those for which maintenance events have been created. The maintenance plan controls what is visible for each selected serial. For more information, refer to the online help file Interval Based Maintenance Programs. Note: It is important to be careful when registering a start or updated value for a serial, since these values are important for result calculations like the due date calculation of interval maintenance.

You cannot record an overhaul that has occurred between existing operational log records or where the latest operational loggings have not been completed. However, as an exception, you will be allowed to report an overhaul prior to all the recorded operational loggings. It is necessary for all the logging dates of the latest logging to be the same for all operational parameters of the serial before you can report and overhaul from the Serial Initialization page.

The different ways of entering performed interval based maintenance depending on how the maintenance plan has been set up, is described in the following subsections. Each subsection will have a defined scenario containing at least what the maintenance plan looks like. In addition to the maintenance plan, the average operational values (per month) and the current operational log values will influence the result of entering the performed interval based maintenance. All the different subsections are referred to as different cases:

Common steps relevant for all subsections

  1. Open the Serial Initialization page, and search for the necessary serial structure.
  2. Click the Interval Maintenance tab, and observe the maintenance codes that appear automatically.
  3. For the maintenance event to be logged, enter a value in the Value At Maintenance field for the primary operational parameter in the upper list.
  4. In the lower list, enter a value in the Value At Maintenance field for the other operational parameters.
  5. Repeat steps 3 and 4 for other maintenance events to be logged.

Common information used by all subsections

Operational ParameterDescriptionAverage Value (per month)
FHRFlight Hours50
LDGLandings20

Case: Enter Values for Recurring Primary Operational Parameter Interval - No Tolerances

Maintenance CodeMaintenance IntervalOperational ParameterCalendar IntervalCalendar UnitRecurring IntervalRecurring Calendar IntervalRecurring Calendar UnitCalculation RuleCycleLower ToleranceUpper Tolerance
A200FHR--200--InspectionNo Cycle--
Operational ParameterLast To DateValue After OverhaulValue Total
FHRMay 1st 201932503250
LDGMay 1st 201915601560
DateValue
April 10th 20193190 FHR
  1. Find the record with Maint Code A.
  2. Enter the maintenance date into the Maint Date field.
  3. In the Value at Maintenance field enter 3190 (which is the value when the maintenance was performed).
  4. In the Value Total field enter 3190 (which is the value when the maintenance was performed).
  5. Ensure that value 3200 is automatically populated in the Maint Interval field. This value tells the application where in the maintenance plan the serial is currently located, and will be the basis for the value of the next maintenance.
  6. Save the record.
Maintenance CodePlanned ValueOperational ParameterDue DatePlanned Date FromPlanned Date ToCalculation Type
A3400FHRSeptember 15th 2019September 15th 2019September 16th 2019Interval
A3600FHRJanuary 13th 2020January 13th 2020January 14th 2020Interval

Case: Enter Values for Recurring Secondary Operational Parameter Interval - No Tolerances

Maintenance CodeMaintenance IntervalOperational ParameterCalendar IntervalCalendar UnitRecurring IntervalRecurring Calendar IntervalRecurring Calendar UnitCalculation RuleCycleLower ToleranceUpper Tolerance
A1160LDG--160--InspectionNo Cycle--
Operational ParameterLast To DateValue After OverhaulValue Total
FHRMay 1st 201932503250
LDGMay 1st 201915601560
DateValue
February 10th 20191450 LDG

3050 FHR

  1. Find the record with Maint Code A1.
  2. Enter the maintenance date into the Maint Date field.
  3. This maintenance code has it's interval defined in a secondary operational parameter, but since the serial also have a value for the primary operational parameter at the time of the maintenance, this must be entered.
  4. In the Value at Maintenance (for operational parameter FHR) field enter the actual value at the time the maintenance was performed, for instance 3050.
  5. In the Value Total field enter the actual value at the time the maintenance was performed, for instance 3050.
  6. Save the record.
  7. Find Oper Param LDG in the lower list.
  8. In the Value at Maintenance field enter 1450 (which is the value when the maintenance was performed).
  9. In the Value Total field enter 1450 (which is the value when the maintenance was performed).
  10. Ensure that value 1440 is automatically populated in the Maint Interval field. This value "tells" the application where in the maintenance plan the serial is currently located, and will be the basis for the value of the next maintenance.
Maintenance CodePlanned ValueOperational ParameterDue DatePlanned Date FromPlanned Date ToCalculation Type
A11600LDGAugust 16th 2019August 16th 2019August 17th 2019Interval
A11760LDGApril 13th 2020April 13th 2020April 14th 2020Interval

Case: Enter Values for Recurring Calendar Interval

Maintenance CodeMaintenance IntervalOperational ParameterCalendar IntervalCalendar UnitRecurring IntervalRecurring Calendar IntervalRecurring Calendar UnitCalculation RuleCycleLower ToleranceUpper Tolerance
A2--150Days-150DaysInspectionNo Cycle--
Operational ParameterLast To DateValue After OverhaulValue Total
FHRMay 1st 201932503250
LDGMay 1st 201915601560
DateValue
March 3rd 20193125 FHR
  1. Find the record with Maint Code A2.
  2. Enter the maintenance date into the Maint Date field.
  3. In the Value at Maintenance (for operational parameter FHR) field enter the actual value at the time the maintenance was performed, for instance 3125.
  4. In the Value Total field enter the actual value at the time the maintenance was performed, for instance 3125.
  5. In the Calendar Interval field use the List of Values to select value 150 d. Observe that Calendar Unit is automatically populated.
  6. Save the record.
Maintenance CodePlanned ValueOperational ParameterDue DatePlanned Date FromPlanned Date ToCalculation Type
A23320 (approx.)FHRJuly 31st 2019July 31st 2019August 1st 2019Calendar
A23570 (approx.)FHRDecember 28th 2019December 28th 2019December 29th 2019Calendar

Case: Enter Values for Recurring Combined Operational Parameter and Calendar Interval - No Tolerances

Maintenance CodeMaintenance IntervalOperational ParameterCalendar IntervalCalendar UnitRecurring IntervalRecurring Calendar IntervalRecurring Calendar UnitCalculation RuleCycleLower ToleranceUpper Tolerance
A3200FHR150Days200150DaysInspectionNo Cycle--
 80LDG--80------
Operational ParameterLast To DateValue After OverhaulValue Total
FHRMay 1st 201932503250
LDGMay 1st 201915601560
DateValue
April 7th 20193170 FHR

1517 LDG

  1. Find the record with Maint Code A3.
  2. Enter the maintenance date into the Maint Date field.
  3. This maintenance code has it's intervals defined in multiple parameters (including calendar time) which means that a value has to be entered for all the intervals using the nominal value. In this particular case it was the LDG interval that triggered the execution of the maintenance.
  4. In the Value at Maintenance field enter 3170 (which is the value when the maintenance was performed).
  5. In the Value Total field enter 3170 (which is the value when the maintenance was performed).
  6. Observe that value 3200 is automatically populated in the Maint Interval field. Change this value to 3800 which is equivalent to the 1520 LDG interval that will be entered later (19 times the initial interval).
  7. In the Calendar Interval field use the List of Values to select value 150 d. Observe that Calendar Unit is automatically populated.
  8. Save the record.
  9. Find Oper Param LDG in the lower list.
  10. In the Value at Maintenance field enter 1517 (which is the value when the maintenance was performed).
  11. In the Value Total field enter 1517 (which is the value when the maintenance was performed).
  12. Ensure that value 1520 is automatically populated in the Maint Interval field.
Maintenance CodePlanned ValueOperational ParameterDue DatePlanned Date FromPlanned Date ToCalculation Type
A31600LDGAugust 16th 2019August 16th 2019August 17th 2019Interval
A31680LDGDecember 14th 2019December 14th 2019December 15th 2019Interval

Case: Enter Values for Recurring Primary Operational Parameter Interval - Tolerances Defined

Maintenance CodeMaintenance IntervalOperational ParameterCalendar IntervalCalendar UnitRecurring IntervalRecurring Calendar IntervalRecurring Calendar UnitCalculation RuleCycleLower ToleranceUpper Tolerance
B200FHR--200--InspectionNo Cycle10%-
Operational ParameterLast To DateValue After OverhaulValue Total
FHRMay 1st 201932503250
LDGMay 1st 201915601560
DateValue
April 8th 20193175 FHR
  1. Find the record with Maint Code B.
  2. Enter the maintenance date into the Maint Date field.
  3. In the Value at Maintenance field enter 3175 (which is the value when the maintenance was performed).
  4. In the Value Total field enter 3175 (which is the value when the maintenance was performed).
  5. Observe that the value -25 is automatically populated in the Correction Value field. The reason for this is that tolerances are defined, and the maintenance is performed outside the tolerances (20 FHR). This value will ensure that the next occurrence of this maintenance code is due 25 FHR earlier.
  6. Ensure that value 3200 is automatically populated in the Maint Interval field. This value "tells" the application where in the maintenance plan the serial is currently located, and will be the basis for the value of the next maintenance.
  7. Save the record.
Maintenance CodePlanned ValueOperational ParameterDue DatePlanned Date FromPlanned Date ToCalculation Type
B3375FHRAugust 31st 2019August 31st 2019September 1st 2019Interval
B3575FHRDecember 29th 2019December 29th 2019December 30th 2019Interval

Case: Enter Values for Recurring Secondary Operational Parameter Interval - Tolerances Defined

Maintenance CodeMaintenance IntervalOperational ParameterCalendar IntervalCalendar UnitRecurring IntervalRecurring Calendar IntervalRecurring Calendar UnitCalculation RuleCycleLower ToleranceUpper Tolerance
B1160LDG--160--InspectionNo Cycle10%-
Operational ParameterLast To DateValue After OverhaulValue Total
FHRMay 1st 201932503250
LDGMay 1st 201915601560
DateValue
January 5th 20191420 LDG

2950 FHR

  1. Find the record with Maint Code B1.
  2. Enter the maintenance date into the Maint Date field.
  3. This maintenance code has it's interval defined in a secondary operational parameter, but since the serial also have a value for the primary operational parameter at the time of the maintenance, this must be entered.
  4. In the Value at Maintenance (for operational parameter FHR) field enter the actual value at the time the maintenance was performed, for instance 2950.
  5. In the Value Total field enter the actual value at the time the maintenance was performed, for instance 2950.
  6. Save the record.
  7. Find Oper Param LDG in the lower list.
  8. In the Value at Maintenance field enter 1420 (which is the value when the maintenance was performed).
  9. In the Value Total field enter 1420 (which is the value when the maintenance was performed).
  10. Ensure that value 1440 is automatically populated in the Maint Interval field. This value "tells" the application where in the maintenance plan the serial is currently located, and will be the basis for the value of the next maintenance.
  11. Observe that the value -20 is automatically populated in the Correction Value field. The reason for this is that tolerances are defined, and the maintenance is performed outside the tolerances (16 LDG). This value will ensure that the next occurrence of this maintenance code is due 20 LDG earlier.
Maintenance CodePlanned ValueOperational ParameterDue DatePlanned Date FromPlanned Date ToCalculation Type
B11580LDGJuly 17th 2019July 17th 2019July 18th 2019Interval
B11740LDGMarch 14th 2020March 14th 2020March 15th 2020Interval

Case: Enter Values for Recurring Calendar Interval - Tolerances Defined

Maintenance CodeCalendar IntervalCalendar UnitRecurring CalculationRecurring Calendar IntervalRecurring Calendar UnitCalendar Interval - Adjust if done earlyCalendar Interval - Adjust if done lateCalculation RuleCycle
B2150DaysYes150DaysNoYesInspectionNo Cycle
B3150DaysYes150DaysYesYesInspectionNo Cycle
B4150DaysYes150DaysNoNoInspectionNo Cycle
B5150DaysYes150DaysYesNoInspectionNo Cycle
Operational ParameterLast To DateValue After OverhaulValue Total
FHRMay 1st 201932503250
LDGMay 1st 201915601560
DateValue
February 1st 20193000 FHR

Combination 1 - How to enter performed interval maintenance for maintenance plans that have the Cal Int. - Adjust if done Late option is enabled:

  1. Locate the record with Maint Code B2.
  2. In the Maint Date field, enter the maintenance date.
  3. In the Value at Maintenance field, enter 3000 (which is the value when the maintenance was performed).
  4. In the Value Total field, enter 3000 (which is the value when the maintenance was performed).
  5. In the Calendar Correction field, enter -10. Note that this value should always be a negative value since the maintenance has been done late.
  6. Save the record.
Maintenance CodePlanned ValueOperational ParameterDue DatePlanned Date FromPlanned Date ToCalculation Type
B23255FHRJune 20th 2019June 20th 2019June 21sr 2019Calendar
B23505FHRNovember 17th 2019November 17th 2019November 18th 2019Calendar

Combination 2 - How to enter performed interval maintenance for maintenance plans that have both the Cal Int. - Adjust if done Early and Cal Int. - Adjust if done Late options enabled:

  1. Locate the record with Maint Code B3.
  2. In the Maint Date field, enter the maintenance date.
  3. In the Value at Maintenance field, enter 3000 (which is the value when the maintenance was performed).
  4. In the Value Total field, enter 3000 (which is the value when the maintenance was performed).
  5. In the Calendar Correction field, enter 10 and/or -10.
  6. Save the record.
Maintenance CodePlanned ValueOperational ParameterDue DatePlanned Date FromPlanned Date ToCalculation Type
B33282FHRJuly 7th 2019July 7th 2019July 8th 2019Calendar
B33532FHRDecember 7th 2019December 7th 2019December 8th 2019Calendar
Maintenance CodePlanned ValueOperational ParameterDue DatePlanned Date FromPlanned Date ToCalculation Type
B33255FHRJune 20th 2019June 20th 2019June 21st 2019Calendar
B33505FHRNovember 17th 2019November 17th 2019November 18th 2019Calendar

Combination 3 - How to enter performed interval maintenance for maintenance plans that do not have the Cal Int. - Adjust if done Early and Cal Int. - Adjust if done Late options enabled:

  1. Locate the record with Maint Code B4.
  2. In the Maint Date field, enter the maintenance date.
  3. In the Value at Maintenance field, enter 3000 (which is the value when the maintenance was performed).
  4. In the Value Total field, enter 3000 (which is the value when the maintenance was performed).
  5. Note that you cannot enter a value in the Calendar Correction field since settings for tolerances (i.e., adjustments when maintenance is performed early or late) has not been defined on the maintenance plan.
  6. Save the record.
Maintenance CodePlanned ValueOperational ParameterDue DatePlanned Date FromPlanned Date ToCalculation Type
B43271FHRJune 30th 2019June 30th 2019July 1st 2019Calendar
B43521FHRNovember 17th 2019November 17th 2019November 18th 2019Calendar

Combination 4 - How to enter performed interval maintenance for maintenance plans that have the Cal Int. - Adjust if done Early option enabled:

  1. Next, locate the record with Maint Code B5.
  2. In the Maint Date field, enter the maintenance date.
  3. In the Value at Maintenance field, enter 3000 (which is the value when the maintenance was performed).
  4. In the Value Total field, enter 3000 (which is the value when the maintenance was performed).
  5. In the Calendar Correction field, enter 10. Note that this value should always be a positive value since the maintenance has been done early.
  6. Save the record.
Maintenance CodePlanned ValueOperational ParameterDue DatePlanned Date FromPlanned Date ToCalculation Type
B53282FHRJuly 7th 2019July 7th 2019July 8th 2019Calendar
B53532FHRDecember 7th 2019December 7th 2019December 8th 2019Calendar

Case: Enter Values for Recurring Combined Operational Parameter and Calendar Interval - Tolerances Defined

Maintenance CodeMaintenance IntervalOperational ParameterCalendar IntervalCalendar UnitRecurring IntervalRecurring Calendar IntervalRecurring Calendar UnitCalculation RuleCycleLower ToleranceUpper Tolerance
B6200FHR150Days200150DaysInspectionNo Cycle10%-
 80LDG--80------
Operational ParameterLast To DateValue After OverhaulValue Total
FHRMay 1st 201932503250
LDGMay 1st 201915601560
DateValue
March 25th 20193152 FHR

1502 LDG

  1. Find the record with Maint Code B6.
  2. Enter the maintenance date into the Maint Date field.
  3. This maintenance code has it's intervals defined in multiple parameters (including calendar time) which means that a value has to be entered for all the intervals using the nominal value. In this particular case it was the LDG interval that triggered the execution of the maintenance.
  4. In the Value at Maintenance field enter 3152 (which is the value when the maintenance was performed).
  5. In the Value Total field enter 3152 (which is the value when the maintenance was performed).
  6. Observe that value 3200 is automatically populated in the Maint Interval field. Change this value to 3800 which is equivalent to the 1520 LDG interval that will be entered later (19 times the initial interval).
  7. Enter value -648 in the Correction Value field. The reason for this is that tolerances are defined, and the maintenance is performed outside the tolerances (20 FHR).
  8. In the Calendar Interval field use the List of Values to select value 150 d. Observe that Calendar Unit is automatically populated.
  9. Save the record.
  10. Find Oper Param LDG in the lower list.
  11. In the Value at Maintenance field enter 1502 (which is the value when the maintenance was performed).
  12. In the Value Total field enter 1502 (which is the value when the maintenance was performed).
  13. Ensure that value 1520 is automatically populated in the Maint Interval field.
  14. Observe that the value -18 is automatically populated in the Correction Value field. The reason for this is that tolerances are defined, and the maintenance is performed outside the tolerances (8 LDG). This value will ensure that the next occurrence of this maintenance code is due 18 LDG earlier.
Maintenance CodePlanned ValueOperational ParameterDue DatePlanned Date FromPlanned Date ToCalculation Type
B61582LDGJuly 20th 2019July 20th 2019July 21st 2019Interval
B61662LDGNovember 17th 2019November 17th 2019November 18th 2019Interval

Case: Enter Values for Non-recurring Primary Operational Parameter Interval

In this case the use of an overhaul (with cycle) is used. The reason for this is that non-recurring maintenance will only be executed once if not combined with an overhaul in the maintenance plan. Entering values for performed interval maintenance, with or without an overhaul, is exactly the same with the exception that without an overhaul there will not be any due dates calculated.

Maintenance CodeMaintenance IntervalOperational ParameterCalendar IntervalCalendar UnitRecurring IntervalRecurring Calendar IntervalRecurring Calendar UnitCalculation RuleCycleLower ToleranceUpper Tolerance
C1000FHR-----InspectionNo Cycle--
OH4000FHR-----OverhaulCycle--
Operational ParameterLast To DateValue After OverhaulValue Total
FHRMay 1st 201932503250
LDGMay 1st 201915601560
Maintenance CodeMaintenance DateValueComment
CJune 1st 20141000 FHR 
OHJanuary 1st 20130 FHRThis maintenance has never been performed. A starting point must be set.
  1. Find the record with Maint Code C.
  2. Enter the maintenance date into the Maint Date field.
  3. In the Value at Maintenance field enter 1000 (which is the value when the maintenance was performed).
  4. In the Value Total field enter 1000 (which is the value when the maintenance was performed).
  5. Ensure that value 1000 is automatically populated in the Maint Interval field. This value tells the application where in the maintenance plan the serial is currently located, and will be the basis for the value of the next maintenance.
  6. Find the record with Maint Code OH.
  7. Enter the maintenance date into the Maint Date field.
  8. In the Value Total field enter 0.
  9. Save the record.
Maintenance CodePlanned ValueOperational ParameterDue DatePlanned Date FromPlanned Date ToCalculation Type
OH4000FHRSeptember 10th 2020September 10th 2020September 11th 2020Interval
C1000FHRMay 3rd 2022May 3rd 2022May 4th 2022Interval

Case: Enter Values for Non-recurring Secondary Operational Parameter Interval

In this case the use of an overhaul (with cycle) is used. The reason for this is that non-recurring maintenance will only be executed once if not combined with an overhaul in the maintenance plan. Entering values for performed interval maintenance, with or without an overhaul, is exactly the same with the exception that without an overhaul there will not be any due dates calculated.

Maintenance CodeMaintenance IntervalOperational ParameterCalendar IntervalCalendar UnitRecurring IntervalRecurring Calendar IntervalRecurring Calendar UnitCalculation RuleCycleLower ToleranceUpper Tolerance
C2500LDG-----InspectionNo Cycle--
OH4000FHR-----OverhaulCycle--
Operational ParameterLast To DateValue After OverhaulValue Total
FHRMay 1st 201932503250
LDGMay 1st 201915601560
Maintenance CodeMaintenance DateValueComment
C2June 1st 2015500 LDG

1200 FHR

 
OHJanuary 1st 20130 FHRThis maintenance has never been performed. A starting point must be set.
  1. Find the record with Maint Code C2.
  2. Enter the maintenance date into the Maint Date field.
  3. This maintenance code has it's interval defined in a secondary operational parameter, but since the serial also have a value for the primary operational parameter at the time of the maintenance, this must be entered.
  4. In the Value at Maintenance (for operational parameter FHR) field enter the actual value at the time the maintenance was performed, for instance 1200.
  5. In the Value Total field enter the actual value at the time the maintenance was performed, for instance 1200.
  6. Save the record.
  7. Find Oper Param LDG in the lower list.
  8. In the Value at Maintenance field enter 500 (which is the value when the maintenance was performed).
  9. In the Value Total field enter 500 (which is the value when the maintenance was performed).
  10. Ensure that value 500 is automatically populated in the Maint Interval field. This value "tells" the application where in the maintenance plan the serial is currently located, and will be the basis for the value of the next maintenance.
  11. Save the record.
  12. Find the record with Maint Code OH.
  13. Enter the maintenance date into the Maint Date field.
  14. In the Value Total field enter 0.
  15. Save the record.
Maintenance CodePlanned ValueOperational ParameterDue DatePlanned Date FromPlanned Date ToCalculation Type
OH4000FHRSeptember 10th 2020September 10th 2020September 11th 2020Interval
C2500LDGSeptember 10th 2022September 10th 2022September 11th 2022Interval

Case: Enter Values for Non-recurring Calendar Interval

In this case the use of an overhaul (with cycle) is used. The reason for this is that non-recurring maintenance will only be executed once if not combined with an overhaul in the maintenance plan. Entering values for performed interval maintenance, with or without an overhaul, is exactly the same with the exception that without an overhaul there will not be any due dates calculated.

Maintenance CodeMaintenance IntervalOperational ParameterCalendar IntervalCalendar UnitRecurring IntervalRecurring Calendar IntervalRecurring Calendar UnitCalculation RuleCycleLower ToleranceUpper Tolerance
C3--1000Days---InspectionNo Cycle--
OH4000FHR-- --OverhaulCycle--
Operational ParameterLast To DateValue After OverhaulValue Total
FHRMay 1st 201932503250
LDGMay 1st 201915601560
Maintenance CodeMaintenance DateValueComment
C3September 27th 20151300 FHR 
OHJanuary 1st 20130 FHRThis maintenance has never been performed. A starting point must be set.
  1. Find the record with Maint Code C3.
  2. Enter the maintenance date into the Maint Date field.
  3. In the Value at Maintenance field enter 1300 (which is the value when the maintenance was performed).
  4. In the Value Total field enter 1300 (which is the value when the maintenance was performed).
  5. In the Calendar Interval field use the List of Values to select value 1000 d. Observe that Calendar Unit is automatically populated.
  6. Find the record with Maint Code OH.
  7. Enter the maintenance date into the Maint Date field.
  8. In the Value Total field enter 0.
  9. Save the record.
Maintenance CodePlanned ValueOperational ParameterDue DatePlanned Date FromPlanned Date ToCalculation Type
OH4000FHRSeptember 10th 2020September 10th 2020September 11th 2020Interval
C31667 (approx.)FHRJune 6th 2023June 6th 2023June 7th 2023Calendar

Case: Enter Values for Non-recurring Combined Operational Parameter and Calendar Interval

In this case the use of an overhaul (with cycle) is used. The reason for this is that non-recurring maintenance will only be executed once if not combined with an overhaul in the maintenance plan. Entering values for performed interval maintenance, with or without an overhaul, is exactly the same with the exception that without an overhaul there will not be any due dates calculated.

Maintenance CodeMaintenance IntervalOperational ParameterCalendar IntervalCalendar UnitRecurring IntervalRecurring Calendar IntervalRecurring Calendar UnitCalculation RuleCycleLower ToleranceUpper Tolerance
C42000FHR30Months---InspectionNo Cycle--
 900LDG-- ------
OH4000FHR-----OverhaulCycle--
Operational ParameterLast To DateValue After OverhaulValue Total
FHRMay 1st 201932503250
LDGMay 1st 201915601560
Maintenance CodeMaintenance DateValueComment
C4June 19th 20151230 FHR

507 LDG

 
OHJanuary 1st 20130 FHRThis maintenance has never been performed. A starting point must be set.
  1. Find the record with Maint Code C4.
  2. Enter the maintenance date into the Maint Date field.
  3. This maintenance code has it's intervals defined in multiple parameters (including calendar time) which means that a value has to be entered for all the intervals using the nominal value. In this particular case it was the LDG interval that triggered the execution of the maintenance.
  4. In the Value at Maintenance field enter 1230 (which is the value when the maintenance was performed).
  5. In the Value Total field enter 1230 (which is the value when the maintenance was performed).
  6. Observe that value 2000 is automatically populated in the Maint Interval field. This value "tells" the application where in the maintenance plan the serial is currently located, and will be the basis for the value of the next maintenance.
  7. In the Calendar Interval field use the List of Values to select value 30 months. Observe that Calendar Unit is automatically populated.
  8. Save the record.
  9. Find Oper Param LDG in the upper list.
  10. In the Value at Maintenance field enter 507 (which is the value when the maintenance was performed).
  11. In the Value Total field enter 507 (which is the value when the maintenance was performed).
  12. Ensure that value 900 is automatically populated in the Maint Interval field.
  13. Save the record.
  14. Find the record with Maint Code OH.
  15. Enter the maintenance date into the Maint Date field.
  16. In the Value Total field enter 0.
  17. Save the record.
Maintenance CodePlanned ValueOperational ParameterDue DatePlanned Date FromPlanned Date ToCalculation Type
OH4000FHRSeptember 10th 2020September 10th 2020September 11th 2020Interval
C41500 (approx.)FHRFebruary 27th 2023February 27th 2023February 28th 2023Calendar

Prerequisites

System Effects