Create Shop Order Requisitions from Proposed Schedule
Explanation
To create shop order requisitions for a production line from its proposed schedule, click
Supply, then Create Shop Order Requisitions from Proposed Schedule. You can
either completely replace the existing shop order requisitions for that time range, or simply add the proposed
schedule as additional requisitions.
This activity is used only when the parts produced on the line is supplied using shop orders.
You can view the shop order requisitions on the Shop Order Requisitions tab.
Prerequisites
- A proposed schedule must exist for the production line.
- A routing revision and alternate valid for this production line must have been selected for each part from
the Routing Operation Parameters dialog box.
System Effects
- Shop order requisitions will be created for the production line, or the selected production line part for the
affected date range. The requisitions will be created with dates and quantities to match the proposed schedule.
The requisitions will be created with the part routing revision and alternate selected in Routing
Operation Parameters for this production line.
- If the Replace Existing Shop Order Requisitions option is enabled, existing requisitions in
status ProposalCreated valid for the production line, or selected production line part will be
deleted for the affected date range. If a requisition is connected to a batch balance, the corresponding balance
node will be removed.