Update Planned Cost from Supplier Price
Explanation
This activity is used to enable the update of the engineering register material procurement list (ERMPL) planned
costs based on supplier price. The latest price changes from the supplier can always be updated on the ERMPL, by
this activity.
This activity can be performed on ERMPL page by accessing Update from
Supplier Price command inside the Update Planned Cost command group..
Prerequisites
- At least one part must be registered on the ERMPL page.
- The part should at least have one supplier defined price.
System Effects
- The planned cost of the ERMPL demand will be updated based on the latest of the primary supplier price.
- The Design Obj. CE Updated option n this page is cleared, if previously selected.