Model: Project - Specifications for Fact Table: PROJECT ACTIVITY INFORMATION

On this page you will find the specifications regarding the Model: Project and Fact Table: PROJECT ACTIVITY INFORMATION.

header for proij act info

Attributes

Attribute Description (where applicable)
Activity Seq Key Represents the Activity Sequence Key of the fact
Control Category Key Represents the Control Category Key

Measures (table to be generated as far as possible)

Aggregation of measures is based on SUM if not explicitly noted.

This section describes the basic measures in the cube. These are either measures defined in the core Information Source, in the model itself or in the ETL process. The columns have the following meaning:

Measure Calculated Y/N Contains Time Intelligence Y/N Definition/Note (where applicable) Aggregation Type Hidden Y/N Tabular Expression
Actual Cost N N N SUM('PROJECT ACTIVITY INFORMATION'[ACTUAL])
Actual Hours N N N SUM('PROJECT ACTIVITY INFORMATION'[ACTUAL_HOURS])
Actual Rev N N N SUM('PROJECT ACTIVITY INFORMATION'[ACTUAL_REVENUE])
Baseline Cost N N N SUM('PROJECT ACTIVITY INFORMATION'[BASELINE])
Baseline Hours N N N SUM('PROJECT ACTIVITY INFORMATION'[BASELINE_HOURS])
Committed Cost N N N SUM('PROJECT ACTIVITY INFORMATION'[COMMITTED])
Committed Hours N N N SUM('PROJECT ACTIVITY INFORMATION'[COMMITTED_HOURS])
Cost Progress % Y N N IF([Planned Cost Progress Basis] > 0 , [Earned Value Cost Progress Basis]/[Planned Cost Progress Basis], BLANK())
Cost Progress % RC Y Y Reporting Currency calculation N IF([Planned Cost Progress Basis RC] > 0 , [Earned Value Cost Progress Basis RC]/[Planned Cost Progress Basis RC], BLANK())
Earned Value Cost N N N SUM('PROJECT ACTIVITY INFORMATION'[EARNED_VALUE])
Earned Value Cost Progress Basis N N Y SUM('PROJECT ACTIVITY INFORMATION'[EARNED_VALUE_COST_EXCLUDE_WAD])
Earned Value Cost Progress Basis RC N Y Reporting Currency calculation N SUM([REP_CURR_EARNED_VALUE_COST_EXCLUDE_FROM_WAD])
Earned Value Hours N N N SUM('PROJECT ACTIVITY INFORMATION'[EARNED_VALUE_HOURS])
Earned Value Hours Progress Basis N N Y SUM('PROJECT ACTIVITY INFORMATION'[EARNED_VALUE_HOURS_EXCLUDE_WAD])
Estimated Cost N N N SUM('PROJECT ACTIVITY INFORMATION'[ESTIMATED])
Estimated Hours N N N SUM('PROJECT ACTIVITY INFORMATION'[ESTIMATED_HOURS])
Estimated Rev N N N SUM('PROJECT ACTIVITY INFORMATION'[ESTIMATED_REVENUE])
Hours Progress % Y N N IF([Planned Hours Progress Basis] > 0 , [Earned Value Hours Progress Basis]/[Planned Hours Progress Basis], BLANK())
Planned Committed Cost N N N SUM('PROJECT ACTIVITY INFORMATION'[PLANNED_COMMITTED])
Planned Committed Hours N N N SUM('PROJECT ACTIVITY INFORMATION'[PLANNED_COMMITTED_HOURS])
Planned Cost N N N SUM('PROJECT ACTIVITY INFORMATION'[PLANNED])
Planned Cost Progress Basis N N Y SUM('PROJECT ACTIVITY INFORMATION'[PLANNED_COST_EXCLUDE_FROM_WAD])
Planned Cost Progress Basis RC N Y Reporting Currency calculation Y SUM('PROJECT ACTIVITY INFORMATION'[REP_CURR_PLANNED_COST_EXCLUDE_FROM_WAD])
Planned Hours N N N SUM('PROJECT ACTIVITY INFORMATION'[PLANNED_HOURS])
Planned Hours Progress Basis N N Y SUM('PROJECT ACTIVITY INFORMATION'[PLANNED_HOURS_EXCLUDE_FROM_WAD])
Planned Rev N N N SUM('PROJECT ACTIVITY INFORMATION'[PLANNED_REVENUE])
Posted Rev N N N SUM('PROJECT ACTIVITY INFORMATION'[POSTED_REVENUE])
Preliminary Rev N N N SUM('PROJECT ACTIVITY INFORMATION'[PRELIMINARY_REVENUE])
Project Margin Y N N [Actual Rev]-[Actual Cost]
Project Margin % Y N N IF([Actual Rev] > 0 , [Project Margin]/[Actual Rev], BLANK())
Scheduled Work Cost N N N SUM('PROJECT ACTIVITY INFORMATION'[SCHEDULED_WORK])
Scheduled Work Hours N N N SUM('PROJECT ACTIVITY INFORMATION'[SCHEDULED_WORK_HOURS])
Used Cost N N N SUM('PROJECT ACTIVITY INFORMATION'[USED])

Time Intelligence Measures

Time based measures are calculated in the cube with respect to other measures. The table below defines the meaning/definition of  the different time measures. These measures need to be used with a specific time dimension hierarchy [REPORTING_DATE].[RepDateMFHy].

Measure Meaning
YTD Aggregated value for current month in current  year. E.g. for period 202010 Ytd represents sum of periods 202000-202010.
R12 For a given period, the sum all months from one year back up to the previous month. E.g. Rolling 12 for 202010 is the sum of months 201910 - 202009
PY Previous Year
The value of the corresponding month one year back. E.g. for month 202010, the value of month 201910.
YTD PY Year to Date Previous Year
Aggregated value for corresponding month one year back. E.g. for month 202010 YTD Previous Year represents sum of months 201901-201910.
R12 PY Rolling 12 (completed) Months Previous Year
For a given month, first going one year back, then taking the sum of all months from one (more) year back up to the previous month. E.g. for month 202010 the sum of month 201810-201909
Avg XXX Ytd Sum XXX YTD/Count XXX YTD
Avg XXX R12 Sum XXX R12/Count XXX R12
XXX % YTD Count XXX YTD/Count YYY YTD
XXX % R12 Count XXX R12/Count XXX R12

USED BY MODEL(S)

Model Name Product Area
Project

Data source Information

The data source for this object is defined using IFS Developer Tool. The data source contains a number of transformations where the model reads data from the last step, i.e. the Data source view name (DW Source View Name).

Additional information can be found in the online documentation of Information Sources.

Model Table DW Source view (SQL Server) BI Access View Referenced Information Source Recommended Access Type
PROJECT ACTIVITY INFORMATION FACT_PROJ_ACTIVITY_INFO_TM FACT_PROJ_ACTIVITY_INFO_BI FACT_PROJ_ACTIVITY_INFO On Line