Start Break
Explanation
This activity is used to start a break. The breaks, defined for the shift, are accessed through
the
Show Breaks command in
My Work. When a break is started, user has option to
pause the ongoing assignments. Setting the ongoing assignments on pause can also be enforced to user via a workflow
configuration. Break starts, the start time of the break is set, and a new command to
End Break is
enabled. The work status icon will update to an amber/orange color.
Prerequisites
An active shift including breaks must exist.
System Effects
As a result of this activity, the break status is changed to started. If the break started is not
the next break, any prior planned breaks, which have not been started, are ignored, and any already started breaks
are ended.