Use this activity to modify requested date on supply requests. In Project Deliverables, the Item cost/hour calculation and schedule generation sets required date on material requirements and material plans. Required date is found on items in the material requirement list, in Project Deliverable Navigator/Materials/Material Requirements tab. Required date is also found on material plans, once those plans have been generated, in Project Deliverable Navigator/Materials/Material Plans tab and in the General tab for the selected planning item, in the tree. Material plans are generated.
If the early finish date on project activity has been changed or if the lead time has been changed, then a new
schedule generation or item/cost hours calculation including generate schedule must be run to reflect the new
required date. If a supply request has already been created for it, the Modify Requested Date menu
option can be selected to change the requested date of the already created supply requests. The Modify
Requested Date option is available in Material Supply tabs (see below) and
enabled when required date and requested date differ.