Perform Project MRP for Part
Explanation
Use this activity to run project MRP for parts, by using a project deliverable structure.
Prerequisites
- An approved project deliverable structure with project defaults and part information, must have been
created.
- Parts should have been defined with the supply option Project MRP.
- Deliverable items must be approved.
- Project activity must be released.
System Effects
As a result of this activity, selective project MRP will be performed and supplies will be planned for the
inventory part(s).