Use this activity to review consume forecast information:
The master scheduling process is used for material with long lead times. Material is requested in an early phase
of the project, by using a temporary project activity. This is done in master scheduling by creating a MS Level 1
part. The material is later transferred to the actual project activity when requested by the project deliverables
process. The material transfer happens during the master scheduling process.
Material created during the master scheduling process is automatically highlighted in project deliverables, by
using a Consume Forecast label. The label is found in Project Deliverables Materials
and Services window:
Part on project deliverable item should have been created as a MS Level 1 part in master scheduling.
Planning item of type Project MRP plan should have been created on project deliverable items.
MS Level 1 part and project deliverable must be connected within the same project.
None.