Insert Activity Milestones

Explanation

Use this activity to insert activity milestones into the project plan. Activity milestones are significant events within the project plan. An activity becomes a milestone automatically when its start and finish dates and times are the same. Alternatively, you can enable the Activity Milestone indicator on the activity, which will result in the activity automatically receiving the same early start and early finish date and time.

Activity milestones are essential for:

Prerequisites

System Effects