This activity is used to disconnect a work order or a work order structure from a project activity. A work order can only be disconnected if the work tasks on the work order does not have any cost lines or invoiceable sales lines.
To disconnect the project activity, go to the Prepare Work Order page or the Active Work Orders page, search for the relevant work order, and click Project Connection. Then, click Disconnect from Activity. If the selected work order is connected to a structure, an information message will appear. Click Yes if you also want to disconnect all work orders below the selected work order in the structure from the project activity. If you click Cancel, it will only disconnect the project activity from the selected work order and underlying work tasks.
As a result of this activity, the work task will be disconnected from the project activity, and underlying work tasks will not appear as a connection on the Project Monitoring > Activity Monitoring - Project Connections page.