View Late Certifications (B2B)
Explanation
This activity can be used by a business-to-business (B2B) supplier (contractor) at any time during the process.
In the subcontract, there can be an agreement about how many days the contract owner has before they need to
respond with a certification. If that date has passed and the application has not yet been certified by the
contract owner, the contractor will receive a notification that the certification is late.
Prerequisites
- The B2B-status in the sub contract valuation should be in status Submitted.
- The status in the sub contract valuation should be Planned, Application Received or Certification In
Progress.
- The Certificate Due Date should have passed.
System Effects
- In the contractor lobby, the counter for late certifications will increase by one.
- When the contractor press the link, the application will open, and the Certification Due
Date will be highlighted so that the contractor can easily see when the application should have been
certified.