Use this to copy one entire master schedule set to another master schedule set for later comparison or for
simulation purposes. For example, if master schedules are planned at the beginning of a planning period and wants
to have it after certain period of time for comparisons to check the deviations from the actual plan, this can be
used to copy your initial master schedule plan to a different master schedule set and use it for later comparisons
as mentioned earlier. You can keep many number of such sets of your plan from different time instances and can use
for comparisons as well.
Note: Copy Entire Master Schedule and Copy Forecast differs from each other. Copy Forecast, copy only the forecast
on a selected set to another while Copy Entire Master Schedule, copy the whole schedule including forecasts and
other scheduling values as well.
To perform this activity, a master schedule activity must be created.
As a result of this activity, the entire level 0 master schedule is copied to the destination MS set. If there was a master schedule already in the destination set, then it will be replaced.