Update Design Object Planned Cost from ERMPL
Explanation
This activity is used to enable the update of the costs and cost elements of the design object from the costs in
engineering register material procurement list (ERMPL). It is useful to receive the latest price changes in the
supplier end into design object planned costs. This activity can be performed on the Project
Connections page for a given design object.
Prerequisites
- At least one part must be registered on the ERMPL page.
- A cost change made to ERMPL must exist. The addition of a cost element with the planned cost or the
modification of existing cost elements is considered a cost change.
System Effects
- The costs along with their related cost elements, of the demand in ERMPL, will be applied to the design
object in IFS/Asset Design.
- The design object's planned cost in the Project/Connections tab will be updated with the
change.
- Design Obj. CE Updated option is ticked in.