Update Requested Costs
Explanation
This activity is used by a business to business (B2B) supplier to update the requested costs for a contract
change order. The contract change order should be set allowing changes by B2B supplier.
Prerequisites
- The status of the contract change order must be in Preliminary or Analysis in Progress
status.
- The B2B Status of the contract change order must be Released or In Progress.
- The contract change order is connected to an active sub contract with B2B supplier set as the supplier.
- The contract owner has added cost elements to the contract change order.
System Effects
The contract change order is updated with the requested costs for the cost elements in the contract change
order.