Purchase Order Created, Manually

Explanation

This activity allows users to manually create a Purchase Order (PO) and PO lines for authorized payment lines in a Contractor Order. Instead of automatic generation, the user initiates the PO creation process.

For Request Bundle Tasks, a dedicated command/API is available to manually create a single consolidated Purchase Order that gathers all eligible payment lines from the Contractor Orders of the tasks within the bundle. This allows the dispatcher or system user to efficiently authorize and track contractor payments in one centralized PO, instead of creating multiple POs for each task. 

If the Self Billing toggle is enabled for the supplier connected to the Service Contractor, then once the PO is created for the Contractor Order, an invoice is created based on the self billing.

Batch Process: Create Purchase Orders for Contractor Orders

To create a purchase order for payment lines from multiple contractor orders the Purchase Orders Creation for Contractor Orders assistant is available.

This assistant will generate one Purchase Order per Service Contractor (or per Contractor Agreement, if applicable), for all authorized Contractor Orders up to a defined date. The batch can be started immediately or scheduled for later execution.

The process includes the following configuration options:

When creating Purchase Orders using the Purchase Order Creation for Contractor Orders assistant, the filtering and date logic ensure accurate data selection:

The system then filters authorized Contractor Orders based on the criteria and creates a PO with multiple lines for the relevant payment lines. Each PO is marked Received and each line as Arrived, enabling consolidated invoicing by contractor and period.

Batch Process: Create Payment Lines and Purchase Orders by Charge Period

A separate batch process supports creating both payment lines and Purchase Orders based on charge periods defined in Contractor Agreements. This allows users to automate the generation of POs and billing events for defined historical or current charge periods. The batch can be scheduled or run on demand and is ideal for ensuring accurate billing aligned with the terms of long-term contractor agreements.

Note: When the supplier invoice is posted, relevant to the created PO, the status of the payment line would get changed to Invoice Received. However, if the invoice gets cancelled the status of the payment line would again become PO created.

Prerequisites

System Effects