Evaluate and Add Modification Events to the Work Scope
Explanation
This activity is used to add one or more modifications to a work scope. Usually the mandatory modifications, due
modifications, and modifications included in the customer baseline (i.e., those which have not been complied with
as yet) are transferred to the work scope. Apart from the mandatory modifications and due modifications, you can
choose the modifications you want added to the work scope. For instance, if a modification which is not due nor
assigned to a serial exists, and this modification is applicable for a particular serial, you can choose to add the
modification to the work scope, as per your requirements.
To add modifications to a work scope, click Assign Events to Work Scope in the
Manage Work Scope Events page. In the Modifications step of the
assistant, select a suitable filter to populate modifications in the list. You can view modifications assigned to
the overhaul object and its structure and modifications included in the baseline. The list will also include
modification not yet due (where pending maintenance events are not yet generated for the modifications). Following
options can be used to include modifications to the work scope:
- Manually add events to work scope, by enabling the Include in Work Scope option for the
required modification and then clicking Assign Selected Events or clicking
Finish.
- Click Select Mandatory Modifications to add all mandatory modifications to the work scope.
Modifications with category Mandatory in the list will be selected automatically. Then click
Assign Selected Events or Finish.
- Click Select Baseline Modifications to add all modifications included in the baseline to the
work scope. Modifications with the Included in Baseline option enabled in the list will be
selected automatically. Then click Assign Selected Events or Finish.
- Search for events based on your requirements, e.g., modification type, then click Select all Queried
Modifications to automatically select the records. Then click Assign Selected Events or
Finish.
To view modifications that have been previously complied with for the overhaul object and its structure, click
the Manage Work Scope Events/PCW Modifications tab. If you want to create a decomply
event, select the relevant modification in this tab and click New Event for Decompliance.
To remove a modification from the work scope, select the relevant modification in the Included Mx
Events tab and click Remove Events from Work Scope.
Note: Only one revision of the modification can be included in the current or any other ongoing work
scope for the overhaul object and its structure. To include a new revision of the modification, the previous
revision must either be removed or canceled from the relevant work scope.
Prerequisites
- The modification should not be complied with.
- The modification must be applicable for the serial part.
- The customers modification baseline must be defined in the Shop Visit Defaults/Modification Baseline
tab.
- The due calculation for modification events must be run to define pending events.
- To add a new revision of a modification, a previous revision should not be included in the current or any
other ongoing work scope for the overhaul object.
System Effects
- The modification events are included in the work scope and will be available for the work scope planning.
This can be verified in the Define Work Scope/Work Scope Mx Events tab.
- The Changes Part Number option is enabled for modifications that result in part number
changes of affected parts. For a single affected part only one such modification can be assigned. An error will
be raised when including modifications to the work scope, if more than one part number change modifications are
included for a single affected part.