Send Full Load
Explanation
Use this activity to force send basic data ( ex: maintenance resources, shifts, materials, additional
qualifications etc.) and scheduling data (ex: Work Task resource activities, materials, dependencies, additional
qualification etc.) to IFS Planning & Scheduling Optimization engine for full schedule calculation.
Prerequisites
- At least one site should be connected to the Maintenance Planning and Scheduling
Dataset.
- Dataset should be set to Active by enabling dataset.
- Connected site(s) must be allowed for the user that has been setup to writes back the changes coming from
scheduling engine to IFS business system.
- For a Work Task to be considered for scheduling using Maintenance Planning and Scheduling:
- There should be resource demand(s).
- Earliest start, latest finish and duration must be specified.
System Effects
- Work Task planned start/ planned finish will be modified as per schedule received from the
scheduling engine.
- Work Assignments will be created for resources planned on individual level.
- Resource Activities connected to the Work Task demands will get updated.
- For Work Tasks not planned, Maintenance Planning and Scheduling Exceptions will be
created.
- IFS Planning & Scheduling Optimization (PSO) scheduling information in Work Task/Additional
information will be updated.