Non Routine
A non routine is a fault that is discovered during the repair phase of a scheduled maintenance which needs to be
corrected in the ongoing work scope. In order to repair a non routine fault, it must be reported on the work order
or work task on which it was discovered.
The non routine can be reported with one of the following fault execution types:
- Report fault - The fault will be repaired as part of the current work
scope.
- Report Partially repaired Fault – This is used to indicate that some work has already been
performed. The time spent by a resource or material utilized for the work can be reported. In addition, it is
possible to enter condition measurement values if condition measurement requirements have been defined for the
task card. The fault is automatically included in the work scope and the task cards and subtasks are set to
finished if all criteria are met.
- Report Already repaired Fault - This is used to indicate that the non routine fault has already been
repaired.
Fault Event
A maintenance event is created automatically in IFS/Fleet and Asset Management when a non routine is reported
with either the Report fault or Report Partially repaired Fault fault execution. The
fault event is added to the maintenance order for the ongoing work scope. If the maintenance order is distributed
with the distribution type,
- Execution Logic Structure - The task cards connected to this event will be transferred automatically
to the relevant work orders based on the ELOs (execution logic orders) in the execution logic structure defined
on the maintenance order. If a relevant work order does not exist, i.e., the ELO is not defined in the execution
logic structure on the maintenance order or the work order for the ELO the task cards are mapped into is already
finished, a new work order will be created automatically and added to the work order structure.
- Work Order - A new work order is created and the task cards that are connected to the event will be
transferred automatically to this work order.
A historical work order is generated when the non routine is registered with the Report Already repaired
Fault fault execution.