Finish Assignment
Explanation
You can select a skill assignment and then select Finish to finish working on the
assignment.
If the assignment you are finishing is the last assignment in the Work Started status and all
other skill requirements are either unassigned or completed, you can also complete the task.
Prerequisites
- The skill requirement should be assigned to you.
- To complete the task while finishing the assignment, ensure there are no other assignments in the
Work Started status.
- For the Overall Panel Status of a maintenance task to be Ready To
Close:
- The maintenance task must be closed and in Complete status.
- All MPC open tasks of it must be signed off.
- Any other maintenance tasks sharing any of its panels must also be in Complete
status.
- For the Overall Panel Status of a maintenance task to be Closed, the MPC
close tasks connected to all of its panels must be signed off.
System Effects
- The status of the skill assignment changes to Completed.
- If you complete the task while finishing the assignment, the status of assignments in the
Assigned status changes to Cancelled.
- If you finish the assignment without starting or recording work, Scheduled Hours are given
as Actual Hours when recording action.
Procedure
- Select the assignment.
- Select Finish, select Record Action, and enter the Action
Taken.
- If needed, update the automatically calculated actual hours.
- Actual hours value is the difference between the start time and the end time. If you adjust the
start time and end time, actual hours are recalculated.
- Select Save.
- If you are using the digital signature service, select Sign, and proceed with the digital
signing process. If you are not using the digital signature service, select Finish.