Transfer to/from Project Inventory
Use this process to change the ownership of inventory between projects, and between the standard inventory and
project inventory. Although similar to the Change Inventory Location scenario, this function only changes the
project belonging of the inventory on-hand, and does not physically move the stock between locations.
Inventory can be categorized according to its ownership as Standard Inventory and Project Inventory. A given
project can own its project inventory, ensuring that the material acquired to its project cannot be issued
to fulfill other demands, from another project or from non-project related demands. This project pegging
distinguishes between what is project material and what is standard material.
Three transferring possibilities are available:
- Transfer from project inventory to standard inventory:
This may be, for example, when a project has excess material that can be used as standard inventory, or when you
do not know which other projects will require the part. This could also be performed before closing the project,
when the project is completed.
- Transfer from standard inventory to project inventory:
This may be, for example, when a project has a use for the material that exists in standard inventory, but the
material needs to be handled as project-specific inventory within the project.
- Transfer from one project inventory to another:
This may be, for example, when a project has excess material that can be used in another project, either during
the project's execution or when the project is about to be completed.
The above transfers can be initiated from the Inventory Part In Stock page according to either one of the
following activities:
- Activity Transfer to Standard Inventory (transferring possibility No.1)
- Activity Transfer to Project Inventory (transferring possibility No. 2 and 3)