Sorting
Explanation
This activity is used to manually sort object before scheduling.
This activity is performed for various reasons.
- Option - Sort by Precedence : When it seems that scheduling is not taking place as expected, the
internal sorting of operations might not have taken place. This manual sorting option would make operations sort
again and scheduling would happen as expected.
- Options - Sort by , LPST, EDD, Work Order Priority : When there are identical orders competing for
same resources thee user can select one of these sorting options and force scheduling logic to give priority to
certain orders based on the sort option.
Prerequisites
Sorting will effect only unscheduled operations/orders
System Effects
The internal sorting order of operations or orders will be re-ordered as per the sort by option.