Create Remanufacturing Shop Order Requisition Manually
Explanation
Use this activity to manually enter a remanufacturing shop order requisition.
To create a remanufacturing requisition manually, create a new record and enter below values:
- Enter the desired part and quantity to remanufacture.
- Select Remanufacturing in the Requisition Type drop-down.
- Enter the date when the remanufactured parts should be available in stock in the Due Date
field.
Prerequisites
- The part being requisitioned must exist as an inventory part with a remanufacturing structure header.
System Effects
- The system creates a shop order requisition with Requisition Type set to
Remanufacturing. From this requisition, you can create a shop order.
- The system automatically generates the requisition number and suggested start date. The start date is
calculated as the entered due date minus the part lead time for the quantity entered. If Plan Manufacturing
Supply on Due Date is enabled for the part, the lead time is compressed with one day since the
remanufacturing is planned to be finished on the same date as the due date.
- If the structure alternate used on the requisition has direct supply with Supply Qty per
Unit > 0 on the Product Structure/Direct Supply page defined, pegged shop
order requisition(s) will be created according to the defined Part, Supply
Type, Supply Qty per Unit and Lead Time Offset.