Create Manufacturing Shop Order Requisition Manually
Explanation
Use this activity to manually enter a manufacturing shop order requisition. You can also generate a shop order
requisition from MRP, Project MRP(PMRP), Master Scheduling, Order Proposals, Next-Level, and similar planning
engines.
To create a manufacturing requisition manually, create a new record and enter below values:
- Enter the desired part and quantity to manufacture.
- Select Manufacturing in the Requisition Type drop-down.
- Enter the date when the manufactured parts should be available in stock in the Due Date
field.
Prerequisites
- The part being requisitioned must exist as an inventory part with a manufacturing structure header.
- To create a requisition manually from the Production Line Management page, a
routing revision/alternate valid for the production line must have been selected using the Routing
Operation Parameters dialog.
System Effects
- The system creates a shop order requisition with the Requisition Type set to
Manufacturing. From this requisition, you can create a shop order.
- The system automatically generates the requisition number and suggests the start date for manufacturing. The
start date is calculated as the entered due date minus the part lead time for the quantity entered. If Plan
Manufacturing Supply on Due Date is enabled for the part, the lead time is compressed by one day since the
manufacturing is planned to be finished on the same date as the due date.
- If the requisition is created from the Production Line Management page, the routing
revision and alternate will be set based on the routing revision/alternate selected for the production line
part.