This activity is used to define operation block settings to configure the operation block when scheduling with Manufacturing Scheduling and Optimization (MSO).
To perform this activity from the Operation Block page, enter or select the relevant values in the appropriate fields.
If it is necessary to schedule preceding and/or succeeding operation blocks along with the current operation block, the Preceding Block and Succeeding Block fields must be set accordingly.
To schedule the operation block with a preferred resource, the Preferred Resource field must be defined.
If the operation block needs to be scheduled at or after a specific start time, enter the desired date and time in the New Start Date/Time field. Similarly, to schedule the operation block at or before a specific finish time, enter the desired value in the New Finish Date/Time field.
If it is necessary to define a new setup time for all operations within the operation block, provide the value in the New Setup Time field.
The Include Operation Blocks toggle must be enabled, and the site must be active on the Finite Scheduling Basic Data page to configure operation blocks from the Operation Block page.
Execute Manual Finite
Scheduling with MSO