Edit Operation Result
Explanation
Use this activity to edit the result of on an existing operation report. This includes reported scrap, quantity
complete, labor and machine times. You can adjust only the values reported on the original report transaction.
- To edit operation result from the Shop Floor Workbench page, expand the operation
and open the Reports tab, then click Edit Result.
- To edit operation result from the Shop Floor Reports page, click Edit
Result.
- To edit operation result from the Time Card and Time Card -
Details pages. Select the relevant report visible in the calendar area and click the
Edit icon.
Prerequisites
To perform this activity:
- The status of the shop order may not be Closed.
- An operation report of the types Report Operation, Scrapping in Operation or Report
Labor must exist.
- Report may not be created from a shop floor clocking. If the report is created from a clocking, result can
only be adjusted by modifying the start/stop time of the clocking record.
- If the Over Reporting list is set to Not Allowed on the Inventory
Part/Manufacturing tab, the sum of the reported quantity complete and scrap must be equal to, or less
than the planned operation quantity plus the defined over report tolerance.
System Effects
As a result of this activity:
- A reversal operation or labor history transaction (UNOPFEED or UNOPFDSCP) is created for the original
operation report transaction.
- A new operation or labor transaction history transaction (OPFEED, OPFEED_SCP or LABOR_RPT) is created with
the updated values.
- If the Adjust Schedule Due To Shop Floor Reporting option has been enabled in the Shop Order
Scheduling Basic Data/Shop Order Scheduling/Scheduling Server tab, the schedule will be adjusted to reflect
the reported time.
- If Buffered Operations Reporting is enabled and the Adjust Schedule Due To Shop Floor
Reporting option is enabled in the Shop Order Scheduling Basic Data/Shop Order Scheduling/Scheduling
Server tab, at the next execution of buffered operations reporting the scheduling server will adjust the
operation time due to remaining quantity and:
- if Prioritize Reported Operation was chosen - the reported operation is given priority and
scheduled as close as possible to now time.
- if Keep Scheduled Operation Sequence was chosen - the schedule will be updated without altering
the previous schedule sequence. Subsequent operations in the same order structure will move closer to the
reported operation in order to fill any capacity gaps which occur immediately after the reported
operation.
- When having operation-linked material line with a connected supply pegging, the issue will reduce the pegged
quantity by the same quantity that was issued. However, if there are more than one supply pegged to the same
demand you will be notified to manually adjust the pegging before the issue can be performed.
- For project connected shop orders in IFS/Project, the Labor, Set-up Labor, Machine and
Set-up Machine Hours will be reported to the project as actual hours according to the project cost
elements that have been defined in the Posting Control setup.