Report Labor Time
Explanation
Use this activity to report labor time for a shop order operation. It can be the time needed to set up an
operation before manufacturing begins (setup time) or the time of the actual manufacturing (runtime). Crew size
indicates the number of people that worked on the operation. A crew size less than 1 indicates a person worked
partly on the operation during its duration.
To report labor for a shop order operation from:
-
Shop Order Operations Reporting or Work Center Operations
Reporting page:
- Select an operation on the Internal Operations tab and click
Report or Report Scrap.
- Enter the time in the Labor Setup Time to Report and/or Labor Time to
Report fields.
- If required, adjust the values in the Setup Crew Size and Crew Size
field.
-
Shop Floor Workbench page:
- Select an operation and click Approve or click Scrap and enable
Report Time.
- Enter the time in the Labor Setup to Report and/or Labor to Report
fields.
- If required, adjust the values in the Setup Crew Size and Crew Size
fields.
- If the time should be registered on specific employee(s), enable Register Time for
Employees and enter the employee(s) that performed the labor in the list.
- Shop Floor Workbench page using the Operation Guide
assistant:
- Select an operation and click Operation Guide.
- Click Approve or click Scrap and enable Report
Time.
- Enter the time in the Labor Setup to Report and/or Labor to Report
fields.
- If required, adjust the values in the Setup Crew Size and Crew Size
fields.
- If the time should be registered on specific employee(s), enable Register Time for
Employees and enter the employee(s) that performed the labor in the list.
- Shop Floor Workbench/Reports tab:
- Select an operation, expand it and select the Reports tab.
- Click New Result.
- Enter the time in the Labor Setup and/or Labor Time fields.
- If required, adjust the values in the Setup Crew Size and Crew Size
fields.
- If time should be registered on an employee, enter this in the Employee field.
-
Shop Floor Reports page:
- Click New Result and then New Operation Result.
- Enter the time in the Labor Setup and/or Labor Time fields.
- If required, adjust the values in the Setup Crew Size and Crew Size
fields.
- If time should be registered on an employee, enter this in the Employee field.
-
My Time Card or Time Card page:
- Click Report Time in the Time Registration section.
- Enable the Shop Order option in the Job Result section.
- Enter the relevant operation ID in the Operation field and select whether to report
setup or runtime in the Time Type field.
- Enter the time in the Hours field and if required adjust the value in the Crew
Size field.
-
My Time Card - Details or Time Card - Details pages:
- Click Report Time in the Intervals and Results section.
- Enable the Shop Order option in the Job Result section.
- Enter the relevant operation ID in the Operation field and select whether to report
setup or runtime in the Time Type field.
- Enter the time in the Hours field and if required adjust the value in the Crew
Size field.
Prerequisites
- The shop order operation must be in at least the Released status.
- To report labor time when reporting scrap, Report Time With Scrap must have been enabled on
the Work Center page for the work center which to the operation belongs, and you must
also report some scrap quantity.
- The operation must have a labor class entered for the respective time type.
- To be able to add an operation result to the time card of an employee, the reporting mode must be
Employee for the site set as primary on the Shop Floor Employees per
Site page.
System Effects
- The status of the operation changes to either Setup Started, Setup Complete or Partially
Reported depending on what you report.
- A labor history (LABOR_RPT) transaction is created.
- If the Adjust Schedule Due To Shop Floor Reporting option has been enabled on the Shop
Order Scheduling Basic Data/Scheduling Server tab, the schedule will be adjusted to reflect the
reported time.
- If Buffered Operations Reporting is enabled and the Adjust Schedule Due To Shop Floor
Reporting option on the Shop Order Scheduling Basic Data/Scheduling Server tab has
been selected, at the next execution of buffered operations reporting the scheduling server will adjust the
operation time due to remaining quantity and:
- if Prioritize Reported Operation was chosen - the reported operation is given priority and
scheduled as close as possible to now time.
- if Keep Scheduled Operation Sequence was chosen - the schedule will be updated without altering
the previous schedule sequence. Subsequent operations in the same order structure will move closer to the
reported operation in order to fill any capacity gaps which occur immediately after the reported
operation.
- For project connected shop orders, the Labor Time and Setup Labor Time will be reported to the
project as actual hours according to the project cost elements that have been defined in the posting control
setup.