Reschedule Shop Order Material Line
Explanation
This activity is used to reschedule a shop order material line and optionally the shop order operation requiring
the material.
To perform this activity from the Inventory Part Availability chart, select a segment
representing a shop order material line demand and click Reschedule.
Prerequisites
A company owned shop order material demand must exist.
System Effects
- The shop order material line will receive a new Required Date according to the value provided in the
dialog.
- If Reschedule Shop Order Operations is off, and the new Required Date is later than the
Finish Date of the operation which to the material line is connected, the operation connection will be
removed.
- If Reschedule Shop Order Operations is off, the new Required Date may not be later than the
Finish Date of the shop order.
If Reschedule Shop Order Operations is enabled:
- Schedule Direction for the operation which to the material line is connected will be set to Forward
Scheduling and the operation will be rescheduled to start the first available work date/time from the given
value. If the material line is not connected to any operation the first operation will be considered.
- Operations parallel to, and succeeding the rescheduled operation will also be set to Forward
Scheduling and rescheduled.
- If the new Required Date is later than the original date, Compress Operations can be set to on.
Then operations preceding the rescheduled operation will be set to Backwards Scheduling and rescheduled
with a Finish Date adjacent to the rescheduled operations new Start Date.
If the site is CBS server enabled, it is only possible to change the Required Date of the material.
Rescheduling of operations (with or without compress operations) is not possible as scheduling individual
operations will be handled by CBS server logic and date required is not an input for operation scheduling. For CBS,
Material cumulative lead time, scheduling capacity setting in the inventory part, supplies and demand situations
for the part will determine the material constraint when scheduling.