Reschedule Shop Order Operation
Explanation
This activity is used to reschedule a shop order operation to a new date/time. The activity can be performed
either using the Reschedule command in the Machine Load and Labor
Load charts, or using drag-and-drop in the Machine Operations Scheduling and
Labor Operations Scheduling charts.
From the Machine Operations Scheduling and Labor Operations Scheduling charts
it is also possible to schedule the operation to a new resource on the same, or a different work center.
Note: New start and finish date will be based on the infinite scheduling logic and may
differ from the value seen in the dialog. For instance, if the provided new start date is on a non working date,
the operation will receive a new start date corresponding to the first available work date/time from the date
provided.
Prerequisites
- The selected chart segment must represent an open shop order operation.
- The Schedule Direction of the shop order may not be set to Manual Scheduling.
- The site of the shop order may not be connected to CBS server.
System Effects
- If the operation is rescheduled to a new resource on the same work center, the new resource will be set as
the Preferred Resource on the operation.
- If the operation is rescheduled to a new resource on a different work center, this work center will be
entered in the Work Center field, and the resource will be set as the Preferred
Resource on the operation.
If Forward Scheduling is selected:
- Schedule Direction for the operation is set to Forward Scheduling and the operation will be
rescheduled to start the first available work date/time from the given value.
- Operations parallel to, and succeeding the rescheduled operation will also be set to Forward
Scheduling and rescheduled.
- If Compress Operations is on, the operation preceding the rescheduled operation will be set to
Backwards Scheduling and rescheduled with a Finish Date adjacent to the rescheduled
operations new Start Date.
If Backward Scheduling is selected:
- Schedule Direction for the operation is set to Backwards Scheduling and the operation will be
rescheduled to finish the last available work date/time before the given value.
- Operations parallel to, and preceding the rescheduled operation will also be set to Backwards
Scheduling and rescheduled.
- If Compress Operations is on, the operation succeeding the rescheduled operation will be set to
Forward Scheduling and rescheduled with a Start Date adjacent to the rescheduled operations
new Finish Date.