Use this activity to define how to split the quantity between the original operation and the new operation. Select the relevant work center for the new operation.
To split an operation from:
In the first assistant step:
In the second assistant step:
A new operation on the shop order will be created. The new operation will have the same sequence operation number as the original. The operation will use the same setup, runtime and crew size by default, but you can modify the new shop order operation after the split or in the adjust assistant.