Schedule Order Structures/Shop Orders/Operations Automatically or Using Drag-and-Drop or Using Insert
Explanation
This activity is used to schedule or reschedule shop order operations, either automatically or using
drag-and-drop or insert of operations. This activity can be used to move individual shop order operations or entire
order structure at a time. The option "schedule" on any object ( for example on an employee) will
schedule the related shop order operations ultimately. This activity description therefore valid for any scheduling
action which is done for any object as it does schedule the related shop order operations finally. The only
exception is, when it comes to resource breaks, the scheduling action on resource break will schedule the resource
break object.
Automatic scheduling shop order:
- In Advanced Planning Board/Activities select the shop order for which you want to perform this
activity.
- Drag the order into the object table area of the Gantt chart while pressing the Shift key. It will be placed
in the object table area with its operations already expanded.
- Select Scheduling. This will open the Change Schedule page.
- Select the required scheduling options from the Scheduling Action(s), Schedule Mode and Resource Assignments
areas.
- The order will be scheduled according to the options selected in step 4. You can see this in the Gantt
chart.
Rescheduling operations using drag-and-drop or insert:
- In Advanced Planning Board/Activities select the shop order for which you want to perform this
activity.
- Drag the order into the object table area of the Gantt chart while pressing the Shift key. It will be placed
in the object table area with its operations already expanded.
- Expand the operation up to the assigned resource level.
- Then place the curser on the required operation on the resource and click.
- Then move the cursor while clicking to a different time slot on the resource.
Note: The cursor will turn into a small downward triangle with the letters INS on it..
- The operation will be inserted to the time slot on the resource by rescheduling the already assigned
operations if there are any.
- You can drag and drop the operations to a new time slot. It will then be rescheduled to occupy that slot if
resource and relationship constraints are met.
Automatic scheduling order structure:
- In Advanced Planning Board/Activities, select the order structure for which you want to perform
this activity ( An order structure could be batch balance id, DOP demand order, interim demand header, or project
Id - which are essentially a collection of shop orders).
- Drag the order structure into the object table area of the Gantt chart while pressing the Shift key. It will
be placed in the object table area with its child shop orders already expanded.
- Select the shop order and Scheduling. This will open the Change Schedule page.
- Select the required scheduling options from the Scheduling Action(s), Schedule Mode and Resource Assignments
areas.
- The order will be scheduled according to the options selected in step 4. You can see this in the Gantt
chart.
- You can select the order structure itself and schedule the entire order structure.
Rescheduling shop orders and operations of an order structure using drag-and-drop or insert:
- In Advanced Planning Board/Activities select the demand order for which you want to perform
this activity.
- Drag the order structure into the object table area of the Gantt chart while pressing the Shift key. It will
be placed in the object table area with its child shop orders already expanded.
- Expand the operation up to the assigned resource level.
- Then place the curser on the required operation on the resource and click ( scheduling by INSERT).
- Then move the cursor while clicking to a different time slot on the resource.
Note: The cursor will turn into a small downward triangle with the letters INS on it..
- The operation will be inserted to the time slot on the resource by rescheduling the already assigned
operations if there are any.
- If you use right click and move, then the operations will be dragged and drop in to a new time slot, and will
be rescheduled to occupy that slot if resource and relationship constraints are met.( DRAG-AND-DROP)
- DRAG-AND-DROP scheduling and INSERT scheduling can be performed on operations as well as in higher level
objects like shop orders, promise shop orders, DOP Orders, DOP headers, batch balance IDs, or any demand order
for that matter. The result would be that the entire set of underlying operations will be rescheduled to a new
time slot ( in the case of DRAG-AND-DROP), or will be scheduled to the new time slot rescheduling other affected
operations in the case of INSERT.
Prerequisites
- The shop orders which are to be scheduled must have been loaded to the advanced planning board, scheduling
client or simulation client.
- The shop orders which are to be rescheduled using drag-and-drop must have been scheduled automatically.
- The shop order or structure must have at least one operation in Scheduled or Released
state.
- The operations may not be in Partially Reported or Reported state.
System Effects
When a work center resource, labor class person or a tool instance is blocked for use, new operations cannot be
scheduled automatically, dragged and dropped or inserted on the blocked resource. Only the operations that are
already scheduled in a blocked resources can be re-scheduled (with maintain resource assignment option selected),
dragged and dropped or inserted on the blocked resources.