Use this to copy one entire Material Planning Scenario to another scenario for later comparison or for
simulation purposes. For example, if master schedules are planned at the beginning of a planning period and wants
to have it after certain period of time for comparisons to check the deviations from the actual plan, this can be
used to copy your initial master schedule plan to a different Material Planning Scenario and use it for later
comparisons as mentioned earlier. You can keep many number of such Material Planning Scenarios of your plan from
different time instances and can use for comparisons as well.
Note: Copy Entire Master Schedule and Copy Forecast commands
differs from each other. Copy Forecast, copy only the forecast on a selected Material
Planning Scenario to another while Copy Entire Master Schedule, copy the whole schedule
including forecasts and other scheduling values as well.
To perform this activity, a master schedule activity must be created.
As a result of this activity, the entire level 0 master schedule is copied to the destination Material Planning Scenario. If there was a master schedule already in the destination scenario, then it will be replaced.