Use this to copy one entire master schedule level 1 material scenario to another scenario for later comparison
or for simulation purposes. For example, if master schedules are planned at the beginning of a planning period and
wants to have it after certain period of time for comparisons to check the deviations from the actual plan, this
can be used to copy your initial master schedule plan to a different Material Planning Scenario and use it for
later comparisons as mentioned earlier. You can keep many number of such Material Planning Scenarios of your plan
from different time instances and can use for comparisons as well.
Note: Copy Entire Master Schedule and Copy
Forecast differs from each other. Copy Forecast, copy only the forecast on
a selected Material Planning Scenario to another while Copy Entire Master Schedule, copy
the whole schedule including forecasts, master production schedule, customer dimensions and supply allocation
values.
To perform this activity, a master production schedule scenario must be created.
As a result of this activity, the entire level 1 master production schedule is copied to the destination Material Planning Scenario. If there was a master production schedule already in the destination scenario, then it will be replaced.