Schedule Work Orders/PM Action Occurrences/Work Tasks/Work Lists Automatically or Using Drag-and-Drop
Explanation
This activity is used to schedule or reschedule work tasks/ PM work lists using the Maintenance Planning Board
(MPB), either manually or automatically. This can be performed on sites which have been set up to use the MPB.
Scheduling can be carried out either automatically or using the drag-and-drop of work tasks/work lists. This
activity can be used to move individual work task/work list or the entire work order, PM action occurrence or
work order structure at a time.
Prerequisites
- The work orders/PM action occurrences which are to be scheduled must have been loaded to the Maintenance
Planning Board.
- The work orders/PM action occurrences which are to be rescheduled using drag-and-drop must have allocated
resources and planned start, finish dates.
- The work orders/PM action occurrences must have at least one work task/work list
System Effects
N/A