DOP Header and DOP Order
DOP Header
The DOP header contains the following information:
- Individual information for each DOP ID.
- Cost information for the DOP structure.
- Information on pegging with customer order lines.
- Connection with project activity.
Creating a DOP header is the first step towards creating a DOP structure. An inventory part with DOP as
the default supply type can be set up in three different ways in order to configure how a customer order line
should behave during release. These are Manual DOP, Automatic DOP, and Release DOP. This
setting will be the default for the DOP connection when a DOP supplied customer order line is created, but can be
changed on the customer order line prior to release. The above setting in the customer order line will be
overridden to Release DOP if a capability check has been performed for a customer order line prior to
release.
- Manual DOP - The DOP header must be created manually and later pegged to the customer order line.
- Automatic DOP - A DOP header is automatically created when releasing a customer order line for the
sales part connected to the inventory part.
- Release DOP - A DOP header is automatically created and a default DOP structure is created and
released when releasing a customer order line for the sales part connected to the inventory part.
Status
Status |
Description |
Created |
A DOP header has been created but does not yet have a DOP structure. |
Unreleased |
The DOP structure has been created for the DOP header. |
Netted |
The netting process has been performed on all or some DOP orders in the structure. |
Released |
Supply orders have been generated for all or some DOP orders in the structure. |
Cancelled |
The DOP header has been canceled. There are no netted parts and no quantity to be
delivered. |
Closed |
The DOP header has been closed. All parts have been delivered to the pegged customer
orders and all underlying DOP orders are closed. |
Settings
When creating a DOP structure, the following settings are available for each DOP header:
- Structure Depth - If the structure depth is set to DOP Parts, DOP orders should be created for
DOP parts and their components having the inventory parts supply type set to DOP. If the structure depth
is set to Full Level, the DOP order should be created for all parts.
- Financial Integration - If Create Values or Auto pre
posting is selected, a code part value is created in IFS/Financials when the DOP structure is created.
If Auto pre posting is selected, the code part value is transferred to all DOP orders in the DOP
structure.
- Auto Release - If Auto Release is enabled, pegged orders will be created automatically for all
DOP orders when the DOP structure is created.
- Allow Changes to DOP Structure - If Allow Changes to DOP Structure is
enabled, it is possible to manually add and remove components (both configurable and not configurable) and
operations within the DOP structure.
-
Netting - Netting means reducing the demand of DOP orders by the inventory quantities available and
excess parts on existing shop and purchase orders. The setting for netting indicates whether the supply for a
DOP order should be made by dedicated orders or netting. Top DOP order will inherit the setting in the DOP
header. Other DOP orders will inherit the setting from inventory part. Possible values are:
- Netting - DOP orders with this setting can be manually netted or will be netted if a netting
process is run for the order or for a parent DOP order.
- No Netting - DOP orders with this setting are not allowed to net excess quantities.
- Auto Netting - DOP orders with this setting will, apart from the functionality of netting DOP
orders automatically get netted when they are released. When automatically initiated the netting processes
on a DOP order, the total branch of the DOP orders will also get automatically netted.
- The settings related to netting supply define from where to net if netting functionality is used. Possible
settings that can be enabled are:
- Inventory - The netting process will reserve parts available in inventory.
- DOP Sourced Supply - The netting process will peg available quantities from existing shop and
purchase orders with demand source DOP Order.
- Inventory Sourced Supply - The netting process will peg available quantities from existing shop
and purchase orders with demand source Invent Order.
Allow Changes to DOP Structure
The Allow changes to created DOP structure setting is used to specify whether it should be possible to
manually add and remove components (both configurable and not configurable) and operations within the DOP
structure. If the top level part is a standard part, the default setting is enabled and for configurable parts it
is disabled.
When configurable parts are added, a default configuration is created based on the configuration defined in the DOP
header. The configuration is set to the Parked status and must be manually edited and set to the
Completed status. Right-click, point to Change DOP Structure and click Add Branch to create
the configured DOP branch. When editing a configuration and a branch has already been created, the branch will be
updated directly when saved. There are no configuration alarms on individual DOP orders.
Note that if the configuration from the customer order demand or top level DOP header is modified and the resulting
configuration alarm is resolved, the existing structure will be replaced with this configuration. Any manually
added components or configuration changes on components will be removed and replaced by the configuration
logic.
DOP Order
DOP orders are the basic elements of the DOP structure. Each DOP ID may have a different product structure. A
DOP order is a structure element equivalent to each part in the bill of material (BOM). A DOP order holds the data
required to manage the acquisition of the part in question. The DOP order contains ordering information. This is
information about how DOP deals with the requirements of each component part. When netting is not carried out, DOP
orders correspond to actual shop/purchase orders, though not necessarily with a one-to-one match. For example, if
additional shop/purchase orders are created as a result of increased demand quantity after release, more than one
order will be pegged to this DOP order. In addition, when pegging is performed, the information on the pegging is
also managed here. Project specific DOP orders will be tagged with the project ID and activity sequence to which
they are connected.
The DOP header's settings are used as the default for netting parameters for the lower DOP order when you
create a DOP structure using a standard BOM. In addition, a parameter corresponding to each existing DOP order is
applied without any change when you create a DOP structure by copying another existing DOP structure. These
parameter settings enable you to support a wide range of production types all from Engineer to order to Make to
stock.
DOP Order Status
Status |
Description |
Created |
The DOP order has been added manually. The status will be changed to
Unreleased once the order is planned. |
Unreleased |
The DOP structure has been generated, but no shop order or purchase requisition has
been created to supply it why you can easily change the date and quantities. |
Netted |
The netting process has been performed for the DOP order. |
Released |
Pegged supply order(s) has been created for the demand quantity of the DOP order. |
Started |
Work has started on at least one of the pegged supply orders. |
Cancelled |
The DOP order will not be used further, and all quantities will be set to zero
(0). |
Closed |
All supply orders have completed the quantity pegged to the DOP order, and all parts
have been delivered to the parent DOP order/customer order/to stock, or unreserved from temp inventory. |
DOP orders within a DOP structure can be planned either backwards or forwards. Backwards planning is the most
common approach, but forwards planning may also be used. See sections Backwards
Planning and Forwards Planning for more information.
Backwards planning of DOP orders in a structure is done in various scenarios, such as when a DOP structure is
created or during upstream date propagation from a parent DOP order to child levels. The topmost DOP order is
planned by aligning its due date with the due date of the DOP header, while a component DOP order is planned by
aligning its due date with the date when it is required by the parent DOP order.
The specific timing of when a component DOP order is required, and therefore how a component DOP order is
planned, varies:
- If Schedule and Create Load for DOP Order Operations is disabled for the site:
- If the component DOP order has no lead time offset, it is planned by setting its due date to the same
date as the start date of the parent DOP order.
- If the component DOP order has a lead time offset, it is planned by setting its due date the lead time
offset number of days before the due date of the parent DOP order, but not earlier than the start date of the
parent DOP order.
- If Schedule and Create Load for DOP Order Operations is enabled for the site:
- If the component DOP order is connected to an operation on the parent DOP order, it is planned by setting
its due date to the same date as the scheduled start date/time of that operation minus the queue time of the
work center of the operation or, if that date is not a working day according to the site manufacturing
calendar, the previous workday.
- If the component DOP order is not connected to any operation on the parent DOP order, it is planned in
the same way as when Schedule and Create Load for DOP Order Operations is disabled.
When the due date of a DOP order has been set, the start date is determined by backwards planning the DOP order,
as described in the section Set DOP Order Start Date by
Backwards Planning.
Forwards planning of DOP orders in a structure is done when performing downstream date propagation from a
component DOP order to parent levels. The due date of the component DOP order determines the planning of its parent
DOP order. If that parent DOP order is a component of another DOP order, its new due date determines the planning
of its parent DOP order, and so on upwards until reaching the topmost DOP order. The DOP header is planned by
aligning its due date with the due date of the topmost DOP order.
Exactly how a parent DOP order is planned varies:
- If Schedule and Create Load for DOP Order Operations is disabled for the site:
- If the component DOP order has no lead time offset, the parent DOP order is planned by setting its start
date to the same date as the due date of the component DOP order. Its due date is then determined by forwards
planning the DOP order, as described in the section Set DOP Order Due Date by Forwards Planning.
- If the component DOP order has a lead time offset, the parent DOP order is planned by setting its due
date the lead time offset number of days after the due date of the component DOP order. Its start date is
then determined by backwards planning the DOP order as described in section Set DOP Order Start Date by Backwards Planning.
- If Schedule and Create Load for DOP Order Operations is enabled for the site:
- If the component DOP order is connected to an operation on the parent DOP order, the due date of the
parent DOP order is determined by forwards scheduling the connected operation, operations that are parallel
to it, and its succeeding operations from the due date of the component DOP order, similar to as described in
the section Set DOP Order Due Date by Forwards
Planning. The start date of the parent DOP order is determined by backwards scheduling the operations
preceding the connected operation from the due date of the component DOP order, similar to as described in
the section Set DOP Order Start Date by Backwards
Planning.
- If the component DOP order is not connected to any operation on the parent DOP order, the parent DOP
order is planned in the same way as when Schedule and Create Load for DOP Order Operations
is disabled.
When the due date of a DOP order has been set, the start date of that DOP order is automatically updated by
planning the DOP order backwards from the due date. The due date of a DOP order is set, for example, when the DOP
order is created, when performing upstream date propagation from a parent DOP order to child levels, and when
manually editing the Due Date field of the DOP order.
For a DOP order with a manufactured part, how the start date is set depends on several factors:
- If Schedule and Create Load for DOP Order Operations is disabled for the site and the DOP
order has a defined routing revision and alternate, or at least one operation:
The fixed and variable lead times are first calculated for the operations of the DOP order. These are then used
together with the order quantity plus the planned supply scrap for that quantity to calculate how many days the
DOP order will take to complete, rounded up. If Plan Manufacturing Supply on Due Date is
disabled for the DOP order part, the start date is then set by subtracting this lead time from the due date of
the DOP order, using the site manufacturing calendar. If it is enabled, the start date is set by subtracting one
day less than the lead time from the due date of the DOP order, also using the site manufacturing calendar.
Note: If the DOP order has no operations, the start date is set to the workday before the due
date if Plan Manufacturing Supply on Due Date is disabled for the DOP order part, using the site
manufacturing calendar. If it is enabled, the start date is set to the same date as the due date.
- If Schedule and Create Load for DOP Order Operations is enabled for the site and the DOP
order has a defined routing revision and alternate, or at least one operation:
The start date is set by scheduling the operations on the DOP order backwards, similar to how shop order
operations are scheduled. The quantity that is used during the scheduling is the order quantity plus the planned
supply scrap for that quantity. If Plan Manufacturing Supply on Due Date is disabled for the DOP
order part, the backwards scheduling starts at the end of the workday before the due date. If it is enabled, the
backwards scheduling starts at the end of the due date. The start date is set to the same day as the scheduling
ends or, if that date is not a working day according to the site manufacturing calendar, to the previous workday.
In case the DOP order has the status Unreleased or Netted and Create
Pegged set to Pegged Orders, machine and labor load of source Scheduled
DOP are created during the scheduling for the DOP order operations based on the quantity remaining to
supply, plus the planned supply scrap for that quantity. The load is distributed over the period during which the
operations are scheduled.
Note: If the DOP order has no operations, the start date is set to the workday prior to the due
date if Plan Manufacturing Supply on Due Date is disabled for the DOP order part, using the site
manufacturing calendar. If it is enabled, the start date is set to the same date as the due date.
- If the DOP order neither has a defined routing alternate nor operations:
The fixed and variable lead times defined for the inventory part of the DOP order are used together with the
order quantity plus the planned supply scrap for that quantity to calculate how many days the DOP order will take
to complete, rounded up. If Plan Manufacturing Supply on Due Date is disabled for the DOP order
part, the start date is then set by subtracting this lead time from the due date of the DOP order, using the site
manufacturing calendar. If it is enabled, the start date is set by subtracting one day less than the lead time
from the due date of the DOP order, also using the site manufacturing calendar.
For a DOP order with a purchased part, if the part has Plan Manufacturing Supply on Due Date
disabled, the start date is set by subtracting the purchasing lead time from the due date, using the site
manufacturing calendar. If Plan Manufacturing Supply on Due Date is enabled, the start date is set
by subtracting one day less than the purchasing lead time from the due date, using the site manufacturing
calendar.
When the start date of a DOP order has been set, the due date of that DOP order is automatically updated by
planning the DOP order forwards from the start date. The start date of a DOP order is set, for example, when
performing downstream date propagation from a component DOP to parent levels without a lead time offset between the
component and the parent, and when manually editing the Start Date field of the DOP order.
For a DOP order with a manufactured part, how the due date is set depends on several factors:
- If Schedule and Create Load for DOP Order Operations is disabled for the site and the DOP
order has a defined routing revision and alternate, or at least one operation:
The fixed and variable lead times are first calculated for the operations of the DOP order. These are then used
together with the order quantity plus the planned supply scrap for that quantity to calculate how many days the
DOP order will take to complete, rounded up. If Plan Manufacturing Supply on Due Date is
disabled for the DOP order part, the due date is then set by adding this lead time to the start date of the DOP
order, using the site manufacturing calendar. If it is enabled, the due date is set by adding one day less than
the lead time to the start date of the DOP order, also using the site manufacturing calendar.
Note: If the DOP order has no operations, the due date is set to the workday after the start
date if Plan Manufacturing Supply on Due Date is disabled for the DOP order part, using the site
manufacturing calendar. If it is enabled, the due date is set to the same date as the start date.
- If Schedule and Create Load for DOP Order Operations is enabled for the site and the DOP
order has a defined routing revision and alternate, or at least one operation:
The due date is set by first scheduling the operations on the DOP order forwards from the beginning of the start
date, similar to how shop order operations are scheduled. The quantity that is used during the scheduling is the
order quantity plus the planned supply scrap for that quantity. If Plan Manufacturing Supply on Due
Date is disabled for the DOP order part, the due date is then set to the workday after the scheduling
ends according to the site manufacturing calendar. If it is enabled, the due date is set to the same date as the
scheduling ends or, if that date is not a working day according to the site manufacturing calendar, to the next
workday. In case the DOP order has the status Unreleased or Netted and
Create Pegged set to Pegged Orders, machine and labor load of source
Scheduled DOP are created during the scheduling for the DOP order operations based on the
quantity remaining to supply, plus the planned supply scrap for that quantity. The load is distributed over the
period during which the operations are scheduled.
Note: If the DOP order has no operations, the due date is set to the workday after the start
date if Plan Manufacturing Supply on Due Date is disabled for the DOP order part, using the site
manufacturing calendar. If it is enabled, the due date is set to the same date as the start date.
- If the DOP order neither has a defined routing alternate nor operations:
The fixed and variable lead times defined for the inventory part of the DOP order are used together with the
order quantity plus the planned supply scrap for that quantity to calculate how many days the DOP order will take
to complete, rounded up. If Plan Manufacturing Supply on Due Date is disabled for the DOP order
part, the due date is then set by adding this lead time to the start date of the DOP order using the site
manufacturing calendar. If it is enabled, the due date is set by adding one day less than the lead time to the
start date of the DOP order, also using the site manufacturing calendar.
For a DOP order with a purchased part, if the part has Plan Manufacturing Supply on Due Date
disabled, the due date is set by adding the purchasing lead time to the start date using the site manufacturing
calendar. If Plan Manufacturing Supply on Due Date is enabled, the due date is set by adding one
day less than the purchasing lead time to the start date, using the site manufacturing calendar.
Release DOP Order
For the release process for DOP, you can specify the scope as follows:
- Full Structure - By selecting a DOP header, you can perform release for the DOP orders of the entire
DOP.
- Branch - By specifying an arbitrary DOP order, you can perform release for the specified order and its lower
orders.
- Specific Order - For an arbitrary DOP order, you can perform release for the selected order only.
The release can be done step by step from a lower level DOP order. This can minimize the impact of changes that
are made after the release; changes made before the release can easily be handled.
A pegged purchase requisition or pegged shop order is created when a DOP order is released for the quantity
remaining to supply after netting. These pegged purchase requisition lines/purchase orders/shop orders are called
pegged orders or supply orders. When a pegged order is released, reservations from the lower components that are
completed owned by the corresponding DOP order will also be transferred to the pegged order. Therefore, there is no
need to reserve again for the pegged order.
Supply orders generated for parts with a scrap factor will be created with a quantity higher than the DOP order
quantity to cover the planned scrap.
Once the DOP order is released, you must be careful when it comes to changing the DOP structure. A DOP order can
be changed until it is set to the Closed status. If the pegged order and the DOP order do not match
concerning time or quantity, the user will receive an alarm. When the DOP order has a shortage, you can create a
new pegged order manually from the DOP order as an additional supply.
Settings
The DOP orders created in the DOP structure will inherit its setting from the DOP header setting as default, but
it can be manually changed if required. The DOP order specific Create Pegged setting indicates whether
pegged orders will be created for the specific DOP order or not, possible values are Pegged Order or No
Pegged Order. The default value is Pegged Order.
Update Flags
There are two lists that indicate up to which status shop orders or purchase orders pegged to the DOP order are
allowed to be updated. The defined value determines the highest status for the DOP pegged shop order or purchase
order when quantity and date changes are allowed.
DOP Pegged SO Update - This value is inherited from the manufactured part settings on the
Manufacturing tab on the Inventory Part page.
DOP Pegged PO Update - This value is inherited from the purchased part setting on the
General tab on the Purchase Part page.
Both these values can be manually changed during the process.
Replication to Supply Orders
Changes made to a DOP order with pegged supply orders can be replicated under the following conditions:
- DOP Order: When the Order Qty or Due Date of the DOP order
is changed, a message will appear allowing the update to be replicated to the pegged supply order. Replication is
only possible if the pegged supply order has a status that permits updates, as determined by the DOP
Pegged SO Update and DOP Pegged PO Update flags.
-
DOP Order Components: The following changes are automatically replicated to the material lines
of the pegged shop order, provided that the supply order has a status allowing updates (according to the
DOP Pegged SO Update and DOP Pegged PO Update flags):
- Adding a new component (new DOP order).
- Removing a component (removing the DOP branch).
- Changing any of the following attributes: Qty per Assembly, Operation,
Component Scrap, or Scrap Factor.
Note: Changes made to DOP components are not replicated to the supplier material lines of
a pegged purchase order.
- Other Changes: Any other modifications made to a DOP order are not replicated to the pegged
supply orders.
Project Connection
If the DOP header is connected to a project activity, the DOP orders in the structure will be tagged with the
project ID and activity sequence. However, not all these DOP orders will necessarily be supplied from inventory and
supplies connected to the same project. This is decided based on the Create Pegged and Std
Planned Item settings for each DOP order:
- If Create Pegged set to Pegged Orders: The DOP order is supplied from
inventory and supplies connected to the same project.
- Else if Create Pegged set to No Pegged Orders and Std
Planned Item set to No: The DOP order is supplied from inventory and supplies
connected to the same project.
- Else Create Pegged set to No Pegged Orders and Std
Planned Item set to Yes: The DOP order is supplied from inventory and
supplies without any project connection.
When DOP orders with Create Pegged set to Pegged Orders are released, the
system generates project connected shop orders or purchase requisitions/orders dependent on the part type. These
orders will be received in the project inventory.