Study MRP Part Information
Explanation
This activity is used to study information about an inventory part which was planned by Material Requirement
Planning (MRP) or Project Material Requirement Planning (project MRP) or by Master Scheduling or Project Master
Scheduling.
- Expected receipts and deliveries of the part
- Existing material/gross requirements
- Planned and proposed receipts from MRP and project MRP
- Material transfer requisitions (MTR) created by multiproject material requirements planning (multiproject
MRP)
- Gross requirements for the part calculated by MRP and project MRP (the requirements when MRP or project MRP
considers only receipts and deliveries, not the quantity on hand)
- Material transfer requisitions (MTR) in the Planned, Released, or Partially Approved
statuses and which do not have a valid source to supply. The value of Exclude will be Yes
to indicate these records were excluded from the project MRP calculation. This will be valid for MTRs with the
Inventory supply type
- The shop order, shop order requisition, or production schedule that generated the demand; if the part is a
component, the parent part is displayed
Prerequisites
- The selected inventory part should be set to be planned by MRP or project MRP by performing site MRP, network
MRP, selective MRP or performing project MRP for activity, project or planning netting groups or by Master
Scheduling or Project Master Scheduling.
System Effects
N/A