Explanation

Use this page to view the low level code assigned for different parts within the Planning Network. Once the MRP is performed for selected Planning Network it calculates low level code for parts within the Planning Network, This will be calculated each time when MRP performed for the selected Planning Network and the results will be updated in this page.

The Low Level Per Network column is updated only after executing a planning network MRP. It does not get updated after performing site MRP/PMRP. Similarly, the Low Level Per Site is updated when executing a site MRP/PMRP calculation, and it does not get updated after performing a planning network MRP. However, on the MRP part record, the low-level code per part is always the one used by the last MRP/PMRP execution.