Reinitiate Demands
Explanation
This activity is used to reinitiate demands for a maintenance order to ensure that any changes to resources
and/or material on a task card or subtask are handled. Any changes in the task library to resources and material on
the task cards or subtasks that are included on the selected event will be retrieved at this time. For material
demands, you have the option of retaining existing reservations and peggings. Following will take place when
resource and material demands are reinitiated:
- Demands that have been added to the task card or subtask on the event will be added to the maintenance
order.
- Demands that have been removed from the task card or subtask on the event will be removed from the
maintenance order.
- Demand lines on the maintenance order will be updated with any changes that have been made to the resource or
material demand in the task library.
To reinitiate demands for a maintenance order, select the Re-initiate Demands option from the
Manage Maintenance Event page. If you want to keep all existing reservations and peggings
for the material on the event., enable the Keep Material Reservations and Peggings option from the
Re-initiate Demands dialog.
Prerequisites
- A maintenance order must exist in the Under Preparation status.
- Events must be connected to the maintenance order, and at least one task card must be connected to the event.
The event should not have the Manual Event event type.
System Effects
- All new and updated resource and material demands associated with the task card will be retrieved. Ownership
of the material will be set based on predefined rules, i.e., based on the part provisioning rules of the contract
connected to the maintenance order or defaulted as company owned stock. If reservations and peggings are retained
as part of this activity, the ownership of these lines will not be changed. For more information on setting
ownership on material demands, refer the activity View Material
Demands.
- If demands have been released on the maintenance order, resource activities will be generated, updated or
removed based on the resource demand changes. Material demands will be released, updated or deleted based on the
changes to material demands.
- If the maintenance order has the Execution Logic Structure distribution type and grouping is done on
resources, task cards and subtasks for which resources were added, changed or removed will be added/copied to the
relevant ELO nodes in the execution logic structure for the maintenance order.