Change Purchase Order Change Order Back to Planned
Explanation
When the purchase order change order has been released, it is no longer possible to register any changes to the
header or lines. If you need to make any further changes to the change order you will need to demote the purchase
order change order back to the Planned status. Then when the new changes are registered you can proceed in the
workflow by releasing the change order once again.
Prerequisites
- A purchase order change order must exist in the Released or Authorized status.
System Effects
- The status of the purchase order change order is updated to Planned and it will be possible to
register further changes to the change order. (Note that this status is not the same as the purchase order
status).
- If purchase authorization is used for the purchase order change order, the authorization rule and routing
will be removed from the change order.