Enter Parts on Supplier Schedule Agreement
Explanation
Use this activity to enter the parts this agreement is valid for, or study parts connected to a supplier
schedule agreement.
Depending on the circumstances, you can handle this in two ways:
- If the tolerances and policies are identical for all parts included in the agreement, the parts are more
easily entered in the Parts tab since these are set as default from the agreement header unless
specifically entered.
- If the tolerances and policies are specific for each customer part, it is advisable to continue to enter the
parts in the page Supplier Schedule Agreement Part.
Prerequisites
- A supplier schedule agreement header must be entered.
- The parts to be connected should be entered in the purchase part record.
- The sites that you need must be entered and connected to your user account.
System Effects
As result of this entry, parts are connected to the supplier schedule agreement.