Update Order Prices from Supplier Agreement
Explanation
Through an automatic background job, this activity is used to update the prices on existing purchase order lines
that use the agreement as a price source with new prices defined in the agreement.
Users can choose which order lines to update based on criteria such as supplier agreement(s), buyer, site and/or
supplier, line status, and a specified date range for the order date, receipt date, or delivery ate. The option is
also available to decide only to update the Planned orders, and the choice can be made to update the orders
directly or based on a scheduled interval. Only agreement lines where the price has been updated for the specified
criteria will be considered in the update process.
Any lines with the price freeze flag enabled will be excluded from the update. If there are open change
orders for a purchase order, the price update will be done on the change order line rather than directly on the
purchase order line.
Authorized orders will be updated based on the setting in the purchase order authorization rule.
Note that:
- Only the order lines that has an existing reference to the agreement will be updated.
- For group agreements, orders on all valid sites will be updated (provided that the user initiating the job
has access to all sites).
- For agreements valid for a supplier hierarchy. Orders related to both the agreement supplier and all
subordinate suppliers will be updated.
- As the new agreement price is considered confirmed both externally and internally there will be no new
revision created for the purchase order.
- This activity can be triggered directly from the supplier agreement, Update Price on Orders command, or
through the navigator, Update Price on Orders for Supplier Agreement.
Prerequisites
- You must have a supplier agreement in a state where the agreement is valid for purchasing. That means either
in status Active or if the status is Negotiate and the setting Effective while
Negotiating is enabled.
- For any orders to be updated, the price on at least one agreement part line should have been updated.
System Effects
The update job will be triggered for the agreement part lines with a Latest Price Update date later than
the Include Lines Modified After date defined for the job and where the Exclude from Order Update is
not enabled:
- The price will be updated on all purchase order lines that refers to the agreement line and where:
- The status of the order line matches the conditions defined for the job
- The order, planned receipt or planned delivery date of the order line falls within the defined valid
from/to period for the job.
- Authorized order lines will be updated if the authorization rule allows automatic updates from
agreements
- There are no open purchase order change order
- The price freeze flag is not enabled
- The price will be updated on all purchase order change order lines that refers to the agreement line and
where:
- The status of the order line matches the conditions defined for the job
- The status of the change order is Planned, Released or Authorized
- The order, receipt or delivery date of the order line is within the valid from/to period defined for the
job
- Authorized change order lines will be updated if the authorization rule allows automatic updates from
agreements
- The price freeze flag is not enabled
Note that the automatic update of prices through this job will not generate a new purchase order
revision. It should be the implicit understanding, both internally and externally, that the price updates based on