Analyze Planning Data
Explanation
This activity describes how to analyze the resulting data after a scheduling calculation. Scheduling is
performed in the Project Scheduler, Project Gantt or in a 3rd party planning tool
followed by an integration of the result to IFS. Information in the project plan can be evaluated through
Project Gantt page which may includes:
- Verifying that the logical relationships between activities are realistic and correct.
- Determining the critical activities and analyzing their impact. Critical activities have a total float less
than or equal to zero.
After analyzing the project plan, it may be necessary to replan and reschedule the project.
Prerequisites
- A scheduling calculation must be performed for the project plan, either in Project Scheduler,
Project Gantt or by retrieving planning data from a third party planning tool.