Close Activity
Explanation
Perform this activity to set the selected project activity to the Closed status. Once an activity is in
Closed status, it can only be demoted to the Completed status.
The Actual Finish date is set to the Early Finish date if Actual Finish has not been set manually.
Note: You are able to to check for any incomplete work on the activity before closing the activity. This
can be done in the Unfinished Activity Work page.
To close an activity, select the activity to be closed and select Close from the
Status command button.
Prerequisites
- The activity should be in either Released or Completed status.
- All work needs to be completed on the activity.
Refer to the activity Generate
Unfinished Activity Work Items to get more information on the work that needs to be finished to be able to
close the activity.
System Effects
- The activity is in the Closed status.
- No more cost, revenue or hours can be registered on the activity.
- Vouchers cannot be created from any related transactions.
- The closed date is set to the current date.
- If the activity belongs to a project PNG, it will be removed from the PNG.