Copy from Budget/Forecast
Explanation
This activity is used to copy budget/forecast version lines, cost/revenue spread and approval routings from one
budget/forecast version to another.
The budget/forecast version into which the copying is done can be a new budget/forecast created at the time of
copying or it can be an existing version devoid of budget/forecast lines or connected snapshots.
There is an option to select if the EAC or ETC should be recalculated to determine the default calculation rule
for snapshot matching in the created forecast.
- If Set ETC Based on Previous EAC is selected: The EAC of the new version is calculated by adding the
connected ETC and the incurred cost of this forecast to the difference between the previous forecast ETC and the
previous connected ETC (of the resource forecast or CCO). The ETC will then be calculated as the difference
between the EAC and the cost until the snapshot date and time.
- If Set ETC Based on Previous ETC is selected: The ETC of the new version is calculated by adding the
connected ETC of this forecast to the difference between the previous forecast ETC and the previous connected ETC
(of the resource forecast or CCO). The EAC will then be recalculated to be the sum of the ETC and the cost until
the snapshot date and time.
If the new budget/forecast version is created from the EAC Workbench, copy from budget/forecast can be done only
when creating the new budget/forecast. EAC Workbench will not allow to copy from budget/forecast after the EAC
Workbench has been created. Further Set ETC Option section will not be available in New Project Forecast assistant
when creating a new forecast version by copying from an existing forecast using the EAC Workbench.
If the EAC Workbench connected to the budget/ forecast version from which the copying is done has Budget
Transfers or Estimated Budget Changes or Estimated Future Commitment values, Copy EAC Workbench Information section
will be visible on New Project Forecast Assistant to copy the required values into the EAC Workbench of the new
Project Forecast version. If selected to copy, values will be directly copied to the respective fields in the EAC
Workbench of the new Project Forecast version created.
Prerequisites
- The budget/forecast version to copy to should not have any defined budget/forecast lines or connected
snapshots.
System Effects
- All budget/forecast lines from the selected budget/forecast to copy from are inserted into the destination
budget/forecast and the connected EAC Workbench.
- The ETC and EAC values of the original budget/forecast will be copied over to the Previous
ETC and Previous EAC fields of the new budget/forecast.
- Any existing cost/revenue spreading may be copied, if selected by the user, and inserted as cost/revenue
spreading on the destination budget/forecast.
- Any approval routing defined on the previous budget/forecast will be copied to the destination
budget/forecast if selected by the user.
- A snapshot is created, if this option has been selected when defining the new budget/forecast
properties.
- Any contract change orders and/or resource forecasts connected to the previous budget/forecast will have its
connections and amounts copied to the destination budget/forecast if selected by the user.
- If the new budget/forecast is created from EAC Workbench;
- Budget Transfers, Estimated Budget Changes and Estimated
Future Commitments will have their values copied to the destination EAC Workbench, if selected by
the user.
- Contract change orders will have its connections and amounts copied to the destination EAC Workbench if
selected by the user. Resource forecasts connections will not be copied to the destination EAC
Workbench.