Delete Activity

Explanation

An activity can be deleted using one of two methods, depending on whether it has connected objects:

Note: When using the Delete Activity action command, connected objects are also deleted. However, if any connected object cannot be deleted—such as a task with reported progress—the system will block the deletion and display an error message.

 

Deleting the Last Activity with Employee Allocations

 If an employee allocation is connected at the project or subproject level, and the Date From and Date To fields in the Resource Planning / Employee Allocation tab have not been manually specified, the system uses the Earliest Start and Latest Finish dates of the last remaining activity to determine the allocation's validity period. In this case, attempting to delete the last activity would result in an undefined validity period, and the system will prevent deletion. To proceed, you must manually enter values in the Date From and Date To fields.

 

Prerequisites

System Effects