Delete Project Demand
Explanation
Perform this activity to remove miscellaneous demand lines, and at the same time delete connected purchase
requisitions or cancel purchase orders, DOP Headers or Shop Orders which have been pegged to those lines.
Prerequisites
- A miscellaneous demand must have been created.
- If a Shop Order, DOP header or a Purchase Requisition Line is created, they should be in a status where
cancelling is allowed.
- If a Purchase Order Line has been created from the Purchase Requisition, the Purchase Order Line must be
cancelled.
System Effects
- The selected miscellaneous demand lines will be deleted.
- If the DOP is allowed to be cancelled, the DOP will be cancelled.
- If the Shop Order is allowed to be cancelled, the Shop Order will be cancelled.
- If Purchase Order have not been created from the connected Purchase Requisition, the Requisition is
deleted.