Enter Estimate to Complete
Explanation
Perform this activity to enter the estimated costs and hours to complete a project activity according to the
relevant cost/revenue elements.
Go to Activity Scope and Schedule page of the relevant activity and enter an estimated
value for the relevant Cost/Revenue Element under the Estimates tab.
Prerequisites
- A project activity must exist.
System Effects
- Estimated costs and hours to complete, with the relevant cost/revenue elements for the project, are specified
for the activity. These values are considered when displaying Performance Analysis for the project.