Insert Activity Milestones
Explanation
Use this activity to insert activity milestones into the project plan. Activity milestones are significant
events within the project plan. An activity becomes a milestone automatically when its start and finish dates and
times are the same. Alternatively, you can enable the Activity Milestone indicator on the
activity, which will result in the activity automatically receiving the same early start and early finish date and
time.
Activity milestones are essential for:
- Highlighting critical points or achievements in the project.
- Providing clear reference markers for progress tracking.
- Improving project visibility and facilitating communication among stakeholders.
- Indicating the completion of major phases or deliverables in the project schedule.
Prerequisites
- A sub project must exist.
System Effects
- As a result of this activity, milestones are created in status Planned.
- Various activity information can be defined for the activity, such as and dependencies and constraints.
- Objects can be connected to or planned on the activity.
- The activity can be registered as a requirement activity in IFS/Project Delivery.
- If the project is connected to a project planned netting group (PNG), the activity will be included in the
connected PNG.