Modify Requested Date
Explanation
The required date is set to the early finish date for the activity. If this date is changed, select the command
Modify Requested Date to reflect the date change in its connected supply.
In Project Deliverables, the required date is set to the early finish date of the activity which has been
connected to the project specific item. If this date has been changed or the project item has been connected to
another activity, then Generate Schedule must be run in order to reflect the new required date for the project
specific item in the MPL. If a supply request has already been created for it, the Modify Requested Date
command can be selected to change the required date of the existing supply.
Prerequisites
- The requested date must be different from the required date.
- A DOP Header in which is either in the Created, Unreleased or Released status must have been created for the
miscellaneous part.
- A Shop Order in either the Planned, Released, Reserved or Started status must have been created for the
miscellaneous part.
- The Purchase Requisition line must be in either the Planned or Released status. If a Purchase Order had been
created from the Purchase Requisition, the Purchase Order must be in either the Planned, Released or Confirmed
status. If execution of the change management functionality in IFS/Purchasing require that a Purchase Order
Change Order should be used to handle changes in a Released Purchase Order, a Purchase Order Change Order must
exist in Planned status.
- Changes must have been done in the early finish date on the connected activity, or the part has been
connected to another activity.
System Effects
- The Due Date on the DOP Header is updated according to the Required Date on the project demand line.
- The Need Date on the Shop Order is updated according to the Required Date on the project demand line.
- The Wanted Receipt Date on the Purchase Requisition line or the Planned Receipt Date on the Purchase Order or
the Purchase Order Change Order line is updated according to the Required Date on the project demand line.
- The Requested Date is updated according to the Required Date on the project demand line.